Combined Synopsis / Solicitation for a potential Supply Chain Management Contract for F108 Engine Support – Mission Analysis
Sources Sought from the Defense Logistics Agency, for work in 0, Oklahoma. Due Oct 26, 2026, 5:00 PM (UTC-4), 7 days left.
| Solicitation number | SPE4AX25RF108-0005 |
|---|---|
| Agency | Defense Logistics Agency |
| Office | DLA Aviation |
| Notice type | Sources Sought |
| Set-aside | None |
| Trade (NAICS) | Other Aircraft Parts and Auxiliary Equipment Manufacturing (336413) |
| Product or service code | 2840 |
| Place of performance | 0, Oklahoma |
| Posted | Sep 24, 2026 |
| Response deadline | Oct 26, 2026, 5:00 PM (UTC-4) (7 days left) |
Official notice and attachments
Description
This notice serves as DLA Weapon Support’s combined synopsis/solicitation as described in FAR 12.603, in accordance with FAR 5.201, and the approved J&A under authority of FAR 6.103-1 and 10 U.S.C. 3204(a)(1), for addition of KC/RC/WC135 Mission Analysis for the CFM56-2 Engine, F108 Model Updates, and an F108 Self-Locking Borescope Plug set certification. This effort is anticipated to be made as an addition to sole source Long Term Contract SPE4AX-25-D-9406 to CFM International Inc. (CFM), Contractor and Government Entity (CAGE) code 58828.
This is a FAR part 12 effort being added to the current contract SPE4AX-25-D-9406. KC/RC/WC135 Mission Analysis, F108 Model Updates, and Borescope certification support services for the United States Air Force (USAF) are being solicited to be added to contract SPE4AX-25-D-9406, awarded to CFM International Inc. CAGE 58828. Actual requirements for the additional scope will be negotiated and added to the basic contract.
Individual requirements are certified as sole source to CFM and synopsized in accordance with FAR 5.201. DLA Weapons Support will issue a letter solicitation (RFP) to the sole source Original Equipment Manufacturer (OEM). If any non-OEM source is interested in providing the entire support for this effort, please notify the Contracting Officer prior to the combined synopsis/solicitation closing date.
A copy of the letter of interest should be forwarded to the Contracting Officer identified herein. The Government may alter the acquisition strategy if it is in the best interest of the Government. In order to receive an award, the contractor must be registered in the System for Award Management (SAM).
SAM registration is at sam.gov.
It is anticipated that this requirement will be added as a separate line item to the current sole source CFM COI contract SPE4AX-25-D-9406. The data required to perform the necessary services is CFM’s proprietary and confidential commercial intellectual data and cannot be shared or provided by the Government. Only sources with access to the F108 series of engines performance information will be considered as a qualified source.
The scope of work is as follows: 1. KC/RC/WC135 Mission Analysis for the CFM56-2 Engine – The contractor shall define the mission characteristics and all variants that the KC135, RC135 and WC135 aircraft fly. The contractor shall assess the validity of engine usage assumptions made during engine certification and, by extension, the Life Limited Part (LLP) Low Cycle Fatigue (LCF) limitations and maintenance intervals published by CFMI.
Since 1985, the KC135, RC135 and WC135 have been operating with the CFM56-2 engines as powerplants. In that time there have been several efforts accomplished by CFMI to verify the flight characteristics of the mission established for these weapon systems. The last assessment was accomplished in 2015, for high pressure system components and drove some changes to LLP lives.
Since it has been a significant amount of time since the last assessment, another mission analysis is recommended to determine if the flight characteristics have changed significantly to impact life limits and maintenance intervals. The contractor shall perform all necessary tasks required to complete an assessment as described above. Using flight data provided by the Air Force and pilot interviews taken by CFMI, analysis will be conducted to establish the mission characteristics and possible impact to cycle definition, LLP limits and maintenance intervals.
Once the contractor has completed the needed analysis and evaluation of the current KC/RC/WC135 missions, they will submit findings and results through their internal review process. Successful review will then drive a report for the Air Force that defines the mission characteristics along with a comparative review of the Air Force’s current mission versus previous mission. These results will be provided in a report to the USAF for USAF review and assessment.
2. F108 Model Updates – The contractor shall update thermal, CAD and stress F108 part models to prepare for future use during lifing analysis, field investigations, design tasks or other program needs. Thermal and stress analyses may be required to support lifing analysis following mission analysis updates; thermal and stress analyses may also be required in the future to support new field investigations or hardware redesign tasks.
Multiple variants may need to be analyzed. Current models were constructed utilizing legacy tools (Patran, PThermal, Flow Network Solver). These models need to be transitioned to the current production tool set by passing them through the model conversion and upgrade process.
This will convert them to Next-Gen Thermal & Flow Simulator. Modifications may be necessary to facilitate this process and ensure that converted model results align with legacy results within acceptable tolerances. Once this process is deemed successful, then additional model variants may be constructed.
Upon completion of this, thermal and stress analyses can be performed. The contractor shall provide a memorandum confirming successful model updates to the USAF for USAF review and assessment. 3.
F108 Self-Locking Borescope Plug set certification – The contractor shall provide a full self-locking borescope plug certification with a service bulletin release that approves the self-locking borescope plug set with a new auto-locking feature, eliminating the need for safety wire. The service bulletin will approve this new design, for us on the CFM56-2B engine configuration (USAF ref F108).
The US Air Force F108 engine fleet has experienced breakages of the borescope plugs which can lead to FOD damage and presents a challenging effort to remove the broken pieces. These breakages are manifested in the 3 borescope plugs located at the stage 7, stage 8 and stage 9 positions of the high pressure compressor. Along with the breakages of these 3 plugs, all borescope plugs require safet
The description continues in the official notice.
About the buyer
The Defense Logistics Agency awarded $46.2 billion in contracts in the last 12 months; its biggest suppliers were Amerisourcebergen Drug Corp, Atlantic Diving Supply, Inc. and W S Darley & Co. See what DLA is buying now.