Upper Wicomico River Dredging Project, Wicomico County, MD
Presolicitation from the Department of the Army. Due Oct 21, 2026, 11:00 AM (UTC-4), 3 days left.
| Solicitation number | W912DR27BA002 |
|---|---|
| Agency | Department of the Army |
| Office | W2SD Endist Baltimore |
| Notice type | Presolicitation |
| Set-aside | Small business |
| Trade (NAICS) | Other Heavy and Civil Engineering Construction (237990) |
| Product or service code | Z1KF |
| Posted | Oct 6, 2026 |
| Response deadline | Oct 21, 2026, 11:00 AM (UTC-4) (3 days left) |
Official notice and attachments
Description
The U.S. Army Corps of Engineers (USACE), Baltimore District will be completing maintenance dredging in the upper half of the Wicomico River, Wicomico County, MD. Material will be placed at an existing upland placement site near the river named Sharps Point located in Salisbury, MD. The Magnitude of Construction is $4,000,000.00 to $8,000,000.00.
The construction duration will be approximately 120 calendar days from Notice to Proceed.The scope includes using a hydraulic dredge and pipeline in the upper portion of the Wicomico River to remove material to its authorized depth of 14 feet. Approximately 250,000 cubic yards of material consisting of silts, sand, clays, mixed shell, gravel and other materials will be dredged and placed at the Sharps Point site.
Minor construction of two weir boxes will also occur at the placement site prior to dredging operations.
About the buyer
The Department of the Army awarded $83.1 billion in contracts in the last 12 months; its biggest suppliers were Lockheed Martin Corporation, Raytheon Company and The Boeing Company. See what Army is buying now.