Home / VA / Facilities Support Services / Notice

B170 Window Recaulking Services

Updated

Solicitation from the Department of Veterans Affairs. Due Oct 29, 2026, 10:00 AM (UTC-5), 7 days left.

Be among the first to see new Facilities Support contracts
Only new notices that match, once a day.
Title as postedZ1DA--B170 Window Recaulking Services
Solicitation number36C25627Q0022
AgencyDepartment of Veterans Affairs
Office256-Network Contract Office 16 (36C256)
Notice typeSolicitation
Set-asideNone
Trade (NAICS)Facilities Support Services (561210)
Product or service codeZ1DA
PostedOct 21, 2026
Response deadlineOct 29, 2026, 10:00 AM (UTC-5) (7 days left)
Add the deadline toGoogle Calendar · Apple / Outlook (.ics)

Official notice and attachments

Description

SF 30 CONTINUATION SHEET AMENDMENT 0002 Solicitation No.: 36C25627Q0022 Project: B170 Courtyard Window Re Caulk CAVHS Purpose of Amendment The purpose of this amendment is to provide the Government s responses to vendor questions submitted prior to the deadline. The following Questions & Answers are hereby incorporated into the solicitation. These clarifications do not change the scope of work unless explicitly stated.

Only the Contracting Officer may authorize changes per FAR 52.212 4(c). SECTION: QUESTIONS & ANSWERS General Administrative Items Q1. Will the Government confirm that offers should be submitted via email to [email protected]?

A1. Yes. Submit one consolidated PDF ( 10MB), font Arial 11, in accordance with the solicitation instructions.

Q2. Are there page limitations? A2.

No page limits apply. The file-size limit of 10MB governs. Q3.

Which form must be submitted SF 1449 or SF 1442? A3. Offerors shall submit a signed SF 1449.

SF 1442 is not required. Evaluation Factors Q4. Please confirm the evaluation factors.

A4. Evaluation consists of: Factor I Approach & Quality Management Factor II Professional Qualifications & Specialized Experience Factor III Past Performance Factor IV Price Factors I III are equal in importance and collectively approximately equal to Price. Q5.

Does managing one subcontractor satisfy Past Performance requirements? A5. Yes, provided the offeror served as the prime contractor.

Site Visit, Access, & Logistics Q6. Will there be a site visit? A6.

A site visit was held on October 14, 2026. No additional site visits will be conducted. Q7.

Please confirm logistical restrictions. A7. Approximate curtainwall height is 50 ft (verify independently).

Elevator weight limit is 4,000 lbs. Courtyard door widths are 36 58 . Quiet hours are 2 3 PM and 10 PM 5 AM.

Coordinate courtyard occupation with nursing staff. Q8. Are badges required?

A8. Not for courtyard work during business hours. Badges are required for roof access.

Delays caused by incomplete contractor submissions are not excusable delays. Scope Clarifications Q9. Does work occur along the entire curtainwall or only at leak locations?

A9. Work shall occur along the entire curtainwall interface within Courtyards 1B and 1C to provide a continuous and complete seal. Q10.

Should the entire length be repaired for a uniform seal? A10. Yes.

Q11. Are cover caps replaced everywhere? A11.

No. Replace only caps that are missing or cannot be reattached. Q12. Are other courtyard walls included?

A12. No. Only the curtainwall/TPO/wall interface is included unless otherwise directed by the CO. Q13.

Will the Government provide as builts or record drawings? A13. No. They are not available.

Q14. Will the Government provide quantities? A14.

No. Offerors must determine all quantities during the site visit. These measurements are binding for proposal purposes. Q15.

Is full perimeter window caulking included? A15. No. Only the interfaces described in the SOW apply.

Q16. Clarify termination bar installation. A16.

Install the bar above the cant strip to secure the existing TPO using fasteners compatible with the substrate. Q17. Clarify face cap/flashing quantities.

A17. Approximately 14 vertical caps have slid; one horizontal cap is missing; two require replacement. Remove flashing attached to the ground level base face cap.

Offerors must verify all quantities. Q18. Will the awning require removal?

A18. Not anticipated. Do not include awning removal unless CO directed.

Q19. How many pavers must be moved and how should they be stored? A19.

Approximately 70 pavers must be moved. Store in the courtyard, stacking no more than six high. Specifications, Submittals, & Warranty Q20.

Which parts of VA 07 54 23 apply? A20. Membrane accessory materials and compatibility requirements apply.

VA 07 92 00 applies to sealant products. Where requirements conflict, the more stringent governs. Q21.

Confirm applicability of installer approvals, warranty, submittals, and pre installation meeting. A21. Manufacturer-approved roofing installer: Not required.

Sealant warranty: 10-year manufacturer warranty required. Submittals: Required for sealants and termination materials showing compatibility. Pre installation meeting: Required prior to NTP; the 30 day PoP begins after NTP issuance.

Q22. Provide TPO manufacturer or warranty info. A22.

Unknown. Contractor is not responsible for maintaining prior warranties and shall ensure compatibility of materials. Schedule & Period of Performance Q23.

Will NTP be flexible due to temperature/weather? A23. Yes.

NTP may be adjusted as appropriate. Excusable delays are handled per FAR 52.212 4(f). Q24.

Are background checks/PIV issuance included in the PoP? A24. Yes.

Badges only required for roof access. Delays arising from incomplete contractor submissions are not excusable. Q25.

Will water spray or infiltration testing be required? A25. No. Optional testing may be performed at the contractor s cost unless CO directed.

Q26. Anticipated award/NTP date? A26.

Award is anticipated on or around November 1, 2026 (subject to change). Schedule adjustments for weather may be considered if CO approved. Labor Standards, Set Aside, Subcontracting, & Bonds Q27.

Which wage determination applies? A27. Davis Bacon Wage Determination AR20260032 applies.

Q28. Will the contract be issued under DBRA only? A28.

Yes. Any SCLS references are not applicable and will be conformed administratively. Q29.

Which limitations on subcontracting apply? A29. Construction limitations apply.

For special trade construction, no more than 75% (excluding materials) may be subcontracted to non similarly situated entities. LOS certification must be submitted. Q30.

Are performance and payment bonds required? A30. No. Bonds are not required under this solicitation unless added by future amendment.

Q31. Confirm SDVOSB status requirements. A31.

This is a total SDVOSB set aside. Offerors must be certified in the SBA database at time of offer and award. Materials &

The description continues in the official notice.

Contracting contact

As published on the official notice. Ask questions in writing and before any questions deadline the notice sets.

Is your business small enough?

For NAICS 561210, a business counts as small if it has no more than $47.0 million in average annual receipts (SBA size standard, with exceptions in the notes). This notice is not set aside, but the size decides your small business status on it. SBA table, current as of Oct 15, 2026.

Notice history

Companies that win this kind of work

Federal contractors paid for facilities support services work, who also hold VA contracts (last 12 months): possible competitors, or partners to team with.

About the buyer

The Department of Veterans Affairs awarded $84.2 billion in contracts in the last 12 months; its biggest suppliers were Optum Public Sector Solutions, Inc., Mckesson Corporation and Triwest Healthcare Alliance Corp. See what VA is buying now.

Facilities Support Services contracts right now

There are 56 open government contract opportunities in this trade (NAICS 561210), 27 posted in the last 7 days; 55% are set aside for small businesses. The agencies buying the most are Department of the Army, Department of the Navy and Department of Veterans Affairs. Most of the work with a stated place is in Virginia, Washington and Georgia. A notice in this trade gives a median of 16 days from posting to deadline; this one gives 8 days.

All open facilities support services contracts

Coming up in this trade

Planned contracts from the agencies' procurement forecasts, often months before a solicitation. Plans can change.

Otay Mesa, Calexico West/East, and Andrade LPOE O&M and VTE Services
General Services Administration
Acquisition Planning · Award FY 2026 · $20M - $49M · Firm Fixed Price
Operations, Maintenance and Vertical Transportation Equipment (OMVTE) Services at the Ronald Reagan Federal Building & Courthouse
General Services Administration
Award FY 2026 · $20M - $49M · Small Business · Firm Fixed Price
PBS R09 FY250030: GSA PBS - O&M & Related Service for Sacramento Federal Buildings
General Services Administration
Acquisition Planning · Award FY 2026 · $20M - $49M · Firm Fixed Price

Recent awards in this trade

From the award notices agencies publish.

Similar open facilities support services bids

Sources Sought for Multi Function Device (MFD) Printer Services Lease
Department of the Army
Due Nov 2, 2026, 4:00 PM (UTC-8) · 11 days left
Sources Sought · Small business · Posted Oct 21, 2026
Solicitation - BWT Operation and Maintenance
Department of the Army
Due Nov 9, 2026, 9:00 AM (UTC-6) · 18 days left
Solicitation · Small business · Posted Oct 21, 2026
Operation and Maintenance of Government-Owned Facilities and Equipment, Jim Woodruff Lock and Dam and Lake Seminole Project, Florida and Georgia
Department of the Army
Due Nov 2, 2026, 2:00 PM (UTC-5) · 11 days left
Solicitation · Small business · Posted Oct 21, 2026
Indefinite Delivery/Indefinite Quantity (IDIQ) Custodial, Pest Control, and Grounds Maintenance Service Contract at U.S. Marine Corps Air Station (MCAS) Iwakuni, Japan
Department of the Navy
Due Nov 3, 2026, 2:00 PM (UTC+9) · 12 days left
Solicitation · Iwakuni, Japan · Posted Oct 21, 2026
JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION (JOFOC) Research Triangle Park (RTP) Facilities Operations & Maintenance Support Services Extension
Environmental Protection Agency
Justification · Posted Oct 20, 2026
Sources Sought National Support Center, Urbana, MD
Social Security Administration
Due Oct 30, 2026, 5:00 PM (UTC-4) · 8 days left
Special Notice · Posted Oct 19, 2026