FAA - W.O. #2023-021108
SECTION 02 41 16
STRUCTURE DEMOLITION
PART 1 - GENERAL
1.1
A.
1.2
A.
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including the FAA General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
SUMMARY
Section Includes:
1.
2.
3.
B.
Related Requirements:
1.
2.
1.3
A.
1.4
Demolition and removal of buildings and site improvements. Abandoning in-place and removing below-grade construction. Disconnecting, capping or sealing, abandoning in-place, and removing site utilities.
Section 01 10 00 "Summary of Work" for use of the premises and phasing requirements.
Section 02 41 19 "Selective Demolition" for partial demolition of buildings, structures, and site improvements.
DEFINITIONS
Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged.
MATERIALS OWNERSHIP
A.
Unless otherwise indicated, demolition waste becomes property of Contractor.
B.
Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1.
Carefully salvage in a manner to prevent damage and promptly return to Owner.
STRUCTURE DEMOLITION
LDG / MMAC IWTP and Collection System Upgrade (Type B)
02 41 16 - 1
FAA - W.O. #2023-021108
1.5
A.
INFORMATIONAL SUBMITTALS
Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control, and for noise control. Indicate proposed locations and construction of barriers.
1.
B.
Schedule of Building Demolition Activities: Indicate the following: 1.
2.
3.
C.
1.6
A.
1.7
Adjacent Buildings: Detail special measures proposed to protect adjacent buildings to remain.
Detailed sequence of demolition work, with starting and ending dates for each activity.
Temporary interruption of utility services.
Shutoff and capping or re-routing of utility services.
Predemolition Photographs or Video: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by demolition operations. Comply with Section 01 32 33 "Photographic Documentation." Submit before the Work begins.
CLOSEOUT SUBMITTALS
Inventory: Submit a list of items that have been removed and salvaged.
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- Attachment 10: Chapter 33 Construction Safety
- Attachment 1a FAA MMAC IWTP Specifications IFC Volume I Rev
- Attachment 2: SF25 Performance Bond
- Attachment 3: SF25A Payment Bond
- Attachment 4: SF24 Bid Bond
- Attachment 5: Past Performance Survey
- Attachment 6: Past Performance Experience Form
- Attachment 7: Client Authorization Letter
- Attachment 9.4.3-CC
- Amendment 1