BRIDGING DOCUMENTS
VA U.S. Department of Veterans Affairs
A
Project Name:
Project Address:
B
A
PARKING GARAGE STRUCTURAL EVALUATIONS
RENO VAMC, 975 KIRMAN AVENUE, NV 89502
B
C
C
DRAWING SHEET INDEX
G-001
COVER PAGE
S-001
STRUCTURAL NOTES AND ABBREVIATIONS
S-100
GROUND LEVEL DAMAGE PLAN
S-100.1
2ND LEVEL DAMAGE PLAN
S-101
REPAIR DETAILS (1)
S-102
REPAIR DETAILS (2)
D
D
E
E
PROJECT SCOPE
F
F
CONSULTANTS
ARCHITECT/ENGINEER OF RECORD
Drawing Title
STAMP
Office of
Construction
and Facilities
Management
248 Copeland Street
Quincy, MA 02169
P: 617-481-6390
F: 617-687-5990
VA FORM 08 - 6231
Phase
BRIDGING DOCUMENTS
NOT FOR CONSTRUCTION
STRUCTURAL NOTES
Approved:
Project Number
PARKING GARAGE REPAIR
Location
U.S. Department
of Veterans
Affairs
Project Title
Building Number
BUILDING 13
Reno VAMC
975 Kirman Ave
Reno, NV 89502
Drawing Scale
N/A
Issue Date
Checked
Drawn
06.26.2026
QS
HA
Drawing Number
G-001
CONCRETE FOR WEATHER EXPOSED STRUCTURE:
1.
HANDRAIL DESIGN SHALL FOLLOW IBC 2018 CHAPTER 1014.
GENERAL NOTES
1.
ALL CONCRETE CONSTRUCTION SHALL CONFORM ACI 301 "SPECIFICATION FOR STRUCTURAL CONCRETE", ACI 305.1, ACI 306.1 UNLESS OTHERWISE NOTED.
2.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO REVIEW AND STAMP THE SHOP DRAWINGS BEFORE SUBMITTAL.
3.
2.
ALL DETAILING, FABRICATION AND PLACING OF REINFORCING REBARS, UNLESS OTHERWISE NOTED, SHALL CONFORM TO ACI 318 "BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE", ACI 117 AND THE ACI DETAILING MANUAL.
SUBMIT FINAL SHOP DRAWINGS INCORPORATING REVIEW COMMENTS/CHANGES TO THE STRUCTURAL ENGINEER OF RECORD FOR RECORD FOR RECORD ONLY.
GENERAL NOTES ON THIS DRAWING REFER ONLY TO STRUCTURAL WORK WITH SCOPE OF WORK LIMITED TO GARAGE REPAIR.
THE STRUCTURAL NOTES ARE INTENDED TO COMPLEMENT THE PROJECT SPECIFICATIONS WHICH ARE PART OF THE CONTRACT DOCUMENTS. SPECIFIC NOTES AND DETAILS ON THE DRAWINGS SHALL GOVERN OVER STRUCTURAL NOTES AND TYPICAL DETAILS.
3.
WORK SHALL CONFORM TO APPLICABLE BUILDING CODES, ORDINANCES, AND REGULATIONS. THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MEANS, METHODS, TECHNIQUES AND PROCEDURES EMPLOYED IN THE PERFORMANCE OF WORK.
4.
THE CONTRACTOR SHALL SUBMIT A WRITTEN REQUEST TO THE STRUCTURAL ENGINEER OF RECORDS BEFORE PROCEEDING WITH ANY CHANGES, SUBSTITUTIONS OR MODIFICATIONS. ANY WORK EXECUTED BY THE CONTRACTOR WITHOUT RECEIVING WRITTEN APPROVAL FROM THE STRUCTURAL ENGINEER OF RECORD WILL BE AT CONTRACTOR'S OWN RISK.
5.
THE CONTRACT DOCUMENTS REPRESENT THE COMPLETED STRUCTURE. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING ADEQUATE TEMPORARY SHORING AND BRACING FOR STRUCTURAL ELEMENTS UNTIL THE ENTIRE