Bid document
Updated
A Word document (157 KB) attached to 642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC, from the Department of Veterans Affairs. Due Nov 20, 2026, 4:00 PM (UTC-5).
File name: 36C24426R0088_1.docx
The full file is for paid members, or buy this bid alone.
Preview
TC "PART I - THE SCHEDULE" \l 1TC "SECTION A - SOLICITATION/CONTRACT FORM" \l 1TC "A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)" \l 2
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS) 10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
calendar days after receiving
award,
notice to proceed. This performance period is
mandatory
YES
NO
a.
envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due. b.
An offer guarantee
is,
is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference. .
d.
considered and will be rejected.
36C24426R0088
X
07-02-2026
642-22-104
36C244
Department of Veterans Affairs
Network Contracting Office 4
Philadelphia VAMC
Philadelphia, PA 19104
Kevin Rodgers
[email protected]
Rogers, Charles T.
215-823-5800 2096
UPGRADE SUBSTATION BLDG 2 PHASE I, PROJECT 642-22-104, PHLVAMC
1.Request for Proposal/Best Value Trade-Off Process. Refer to evaluation factors and selection criteria.
2.The magnitude of construction project is between $5,000,000 and $10,000,000.
3.Prior to commencement of work, general contractor shall provide proof that an OSHA certified "competent person' (CP) will maintain a presence at the work site whenever the general or subcontractors are present.
4.Contractor Personnel Security Requirements: All contractor personnel may be subject to fingerprinting and background
The beginning of the document. Download the full file to read on.