Defense Logistics Agency

DLA Installation Management Richmond

DM-FRIE

B34 and B42 DWV System Smoke Testing & Hydro Jetting
P.2026.00774

STATEMENT OF WORK (SOW)

1. OBJECTIVES

The Contractor shall provide all labor, supervision, materials, equipment, and incidentals necessary to perform smoke testing, hydro jetting and evaluations of the drain, waste and vent system.

2. BACKGROUND

Buildings 34 and 42 has experienced an intermittent sewer odor throughout the facilities. The Government requires a comprehensive evaluation of the Drain, Waste, and Vent system to identify potential defects, leaks, obstructions, improper connections, and other deficiencies contributing to the odor. No repairs are authorized under this contract. The purpose of this effort is to document the existing condition of the entire DWV system and provide recommendations for future corrective actions.

3. SPECIFIC REQUIREMENTS

o Perform a complete smoke test of the entire DWV systems. o The Contractor shall introduce a non-toxic, non-staining plumbing smoke, or another industry approved standard testing medium, into the DWV systems. o The smoke used shall be specifically manufactured and intended for plumbing system testing.
o If an alternative testing method is proposed, the Contractor shall obtain written approval from the PM prior to use and demonstrate that the method provides an equivalent level of leak detection.
o Identify and document all locations where smoke is observed. o The Contractor shall hydro jet the entire accessible sanitary drain systems, including horizontal mains, branch lines, building sewer and vertical stacks where practical. o The Contractor shall perform a CCTV inspection of the entire accessible DWV systems and provide a USB thumb drive with footage of the inspection. o Provide a comprehensive written inspection report and a summary of smoke test findings and a complete hydro jetting report.
o No repairs shall be performed under this contract.
o If conditions requiring repairs are identified, the Contractor shall document the deficiency and include the location and recommend corrective action in the final report. o Due to building occupancy, all work shall be performed after normal business hours. o Normal business hours are between 0600-1800, Monday-Friday.

4. CONTRACTOR QUALIFICATIONS

The contractor must demonstrate a minimum of three years of documented experience in performing work of similar scope and complexity involving commercial Drain, Waste, and Vent

The beginning of the document. Download the full file to read on.