STATEMENT OF WORK

MDC Brooklyn- B&F PROJECT 26Z2AV2

BRO INTERIOR REPAIRS EAST PARTITIONS

SPECIFICATIONS

A. SCOPE OF WORK

The contractor shall remove and replace all existing shower partitions (with attached changing rooms) and bathroom stall partitions on the 2nd, 3rd, 4th, 5th, and 6th floors of the East Building at MDC Brooklyn. Each floor contains a North and South side, and each side includes:
• 6-bathroom stalls
• 7- shower stalls with changing rooms
• Changing rooms shall be 39.5 inches deep and include a door All partitions shall be floor- and overhead-braced. Materials and finishes shall include: • Powder-coated steel partitions
• 58-inch doors and panels
• Chrome zamac hardware
• Silver Vein color for all doors and panels
All work will occur in occupied housing areas, requiring coordination with the COR for access and movement. Contractor shall also remove and replace all affected existing restroom accessories including, but not limited to, handicap grab bars, toilet paper holders, sanitary napkin dispenser, towel bars, soap dispensers, etc. Contractor to provide industrial standard labor and materials warranties from date of substantial completion.

B. QUALITY ASSURANCE /INSTALLATION REQUIREMENTS

All installation work shall comply with manufacturer specifications for the products installed. The contractor is responsible for obtaining all field measurements necessary to ensure proper fit and installation.

C. UTILITIES

1. The FBOP will provide restrooms, water or electricity service of any kind.

D. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor shall:
•

Always maintain a clean and orderly work area

•

Remove debris, scrap, and rubbish daily

•

Remove all surplus materials and equipment upon project completion

•

Dispose of all waste in accordance with Federal, State, and local laws

•

Any damage to Government property caused by contractor personnel shall be repaired or replaced at no cost to the Government.

•

E. SUBMITTALS

•

The contractor shall provide:

•

Equipment and material submittals within 15 days of receiving the Notice to Proceed.

•

Security clearance packets for all personnel 14 working days prior to the start of work.

•

Daily employee roster verifying all workers onsite are cleared and approved.

•

Any deviation from this SOW must be submitted as a Change Order Request and approved by the Contracting Officer prior to implementation.

F. CONTRACTOR SECURITY/WORKING REGULATIONS:

A. WORK HOURS

•

Standard work hours: 7:00 AM – 3:00 PM, Monday–Friday (excluding federal holidays).