Statement of Work (SOW)
Replace Perimeter Security Fence
564-23-701
Veterans Health Care System of the Ozarks (VHSO)
Fayetteville, Arkansas
The Contractor shall furnish all management, supervision, labor, material, equipment, tools, supplies, consumables, parts, and related services, in accordance with the SOW, drawings, and specifications to fully complete the replacement of existing perimeter fence, replacing a gate, and automating all gates (Gate #1 through Gate #8) . This is a phased project and shall be completed in accordance with the contract documents. Electronic Portable Document Format (.pdf) copies of drawings and specifications to this work will be furnished by VA upon Contractor’s written request to the Contracting Officer (CO). Hard copies of SOW, drawings, and specifications are the Contractor’s responsibility and expense at no additional cost to the Government. Contractor is responsible to verify existing and new dimensions, locations, and quantities to complete this project located on the VHSO Main Campus 1100 N. College Avenue, Fayetteville, AR 72703.
**The Certification and Accreditation (C&A) does not apply, a Security Accreditation Package is not required**
I.

GENERAL:

A.

Any provision or partial provision of the Contract, including but not limited

to, drawings and specifications that is not consistent with this SOW will be null and void only to the extent of the inconsistency. All other provisions or partial provisions of the Contract, including but not limited to, drawings and specifications, shall remain in full force and effect.
B.

Safety shall be the Contractor’s highest priority.

C.

Period of Performance: Three Hundred Sixty Five (365) calendar days.

D.

This project shall be a turn-key operation in accordance with this SOW,

drawings, and specifications to be complete and working system(s). E.

VHSO facility shall continue to operate during the contract Period of

Performance, including but not limited to, roadways and electrical systems.

564-23-701 Replace Perimeter Security Fence SOW Rev. 1

F.

Contractor’s work shall be conducted with the least amount of disruption

to the VHSO facility.
G.

Contractor shall submit to the CO and CO Representative (COR) a

Schedule of Values (SOV), Field Office Expenses, and a Project Schedule (including Phasing Control Plan if applicable) in accordance with this SOW, drawings, and specifications no later than ten (10) calendar days after Notice to Proceed (NTP) for COR written approval. The Project Schedule shall contain