WOMBLE WORK CENTER FIBER OPTIC INSTALLATION
USDA FOREST SERVICE
OUACHITA NATIONAL FOREST
WOMBLE RANGER DISTRICT
MT IDA, ARKANSAS
SPECIFICATIONS INDEX
DIVISION 01 00 00 GENERAL REQUIREMENTS
o SECTION 01 10 00 SUMMARY OF WORK
o SECTION 01 31 13 COORDINATION
o SECTION 01 33 00 SUBMITTAL PROCEDURES
o SECTION 01 45 00 QUALITY CONTROL
o SECTION 01 77 00 PROJECT CLOSEOUT
DIVISION 27 00 00
o SECTION 27 10 00 TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 31 00 00
o SECTION 31 05 16 AGGREGATES FOR EARTHWORK
DIVISION 32 00 00
o SECTION 32 91 00 PLANTING PREPARATION
o SECTION 32 92 00 TURF AND GRASSES
DIVISION 01 00 00 GENERAL REQUIREMENTS
01 10 00 – SUMMARY OF WORK
The project is located at 24 Forbes Road, Mt Ida, AR 71957 at the Womble Work Center. The contractor shall provide all labor, tools, equipment, and materials to perform the work listed below per the specification.
A. Install two inch non metallic conduit and pull boxes from the Ranger Office to the Work Center 18 inches deep minimum.
B. Install fiber optic cable from the Office network closet to the Work Center network closet. C. Backfill areas around conduit and pull boxes and disturbed areas to natural grade. D. Seed, fertilize, and mulch all disturbed areas in accordance with specifications below.
01 31 13 – PROJECT COORDINATION
The contractor shall perform work in a manner that will protect the safety of public and employees. The contractor shall perform the work between the hours of 8:00 AM and 4:30 PM Monday through Friday excluding Federal Holidays unless arrangements have been made with the COR.
01 33 00 – SUBMITTAL PROCEDURES
The contractor shall furnish submittals on all items they intend to use including the brand names listed in the specifications. Submittals shall be made within fifteen (15) days prior to commencing any work that relates to a respective submittal. Approvals are not automatic. Incomplete information on the proposed items will result in rejection.
The contractor shall submit electronic sets of the manufacturer's description of all "or equals" proposed materials specified. This description shall include:
1) Product name and model number
2) Manufacturer
3) Product description (include sizes if different from specified" 4) Technical data
5) Warranty
All differences between the specifications or name brands listed shall be highlighted on the submittal noting all differences.
01 45 00 – QUALITY CONTROL
It is the Government's intent that expert and experienced workers perform the work described in this