USCG RB-M 45709 FM-200 Cylinder Replace - Statement of Work (SOW) Project: Replacement of FM-200 Fire Suppression Cylinder Vessel: U.S. Coast Guard 45’ Response Boat–Medium (RB-M) Location: 196 Tradd St, Charleston, SC 29401
Prepared by: Joseph Gauvain

1. Purpose

This Statement of Work defines the tasks, materials, labor, and testing requirements necessary to remove, replace, and certify the FM-200 (Heptafluoropropane) clean agent fire suppression cylinder installed aboard a U.S. Coast Guard 45’ RB-M. Work will ensure compliance with USCG, NFPA 2001, and manufacturer specifications.

2. Scope of Work

The contractor shall provide all personnel, tools, materials, equipment, and supervision required to perform the FM-200 cylinder replacement, including system recharging, functional testing, and documentation. The work includes, but is not limited to, the following:

2.1 Pre-Work Requirements

Verify power to the fire suppression panel is secured and tagged out per USCG and facility safety procedures. Review system drawings, cylinder specifications, nozzle locations, and flow calculations. Inspect existing FM-200 system components for compatibility with replacement cylinder (actuators, piping, pressure switches, brackets, and fittings).

2.2 Removal of Existing Cylinder

Remove cabinet fasteners, hold-down hardware, or straps securing the current cylinder. Disconnect mechanical discharge piping and actuation lines. Safely remove the expired/depleted cylinder from the vessel following EPA and manufacturer handling guidelines. Transport and dispose of or return the old cylinder in accordance with applicable environmental regulations.

2.3 Installation of New FM-200 Cylinder

Provide and install a new FM-200 cylinder of identical size, pressure rating, and agent weight as specified by OEM for the RB-M engine compartment system. Install mounting brackets hardware.
Connect discharge piping, actuation mechanism (electric/pressure), pressure switches, and all associated hardware. Verify all fittings are torqued to manufacturer specifications and that no leaks are present.

2.4 System Commissioning

Check system pressure, agent weight, and cylinder date codes.

3. Deliverables

The contractor shall provide the following upon completion: Certificate of Installation and System Recharge
Updated cylinder tag including agent weight, pressure, and hydrostatic test date System test report detailing all verification steps
Copy of material certifications (FM-200 OEM)

4. Standards and Compliance