Lease of Office Space in Philadelphia, PA Request for Lease Proposals (RLP) #26NAT02
6PA0364 RLP & Lease Changes:
Paragraph 1.05 of the RLP (R100_AAAP) and Paragraph 4.01 of the Lease (L100_AAAP) is hereby modified to remove the “AAAP Construction Schedule” and replace it as follows. Note that “Days” are defined as “Working Days”.
·
Design Kick Off Meeting with Lessor, GSA & Agency (after lease Award): 10 DAYS ·
Lessor-Provided Design Intent Drawings (DIDs): 20 DAYS
·
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings: 15 DAYS
·
Lessor Corrects/Finalizes DIDs: 10 DAYS
· Lessor Prepares and Submits 65% CDs: 20 DAYS
·
Government Reviews 65% CDs: 15 DAYS
·
Lessor Prepares and Submits 95% CDs: 20 DAYS
·
Government Review of 95% CDs: 15 DAYS
·
Lessor Prepares and Submits Updated CDs 100%: 10 DAYS
·
Final Review by GSA/Agency: 10 DAYS
·
Lessor Preparation and Submission of the TI and BSAC Price Proposal: 30 DAYS ·
Government reviews TI/BSAC Bids and Provides Comments: 15 DAYS ·
Lessor Submits Revised TI Bids: 10 DAYS
·
Government Reviews Revised TI Bids and Provides Additional Comments (if needed): 10
DAYS
·
Construction Kick Off Meeting: 10 DAYS
·
Lessor Completes Construction of TIs and Completion of Other Required Construction Work: 130 DAYS
·
Acceptance Inspection/Generate Punchlist: 5 DAYS
·
Punchlist Completed: 15 DAYS
In the event of a conflict between the Lease (L100) Section 5 general language and the tenant’s special requirements, the more stringent tenant requirements will be adhered to.