RGNF Asbestos Mitigation
1240L27Q0010
Question and Answers

1. Schedule of Items line 2 (South Fork) reads "Remove existing asphalt shingle roofing system to deck," while the SOW and testing report list 60 SF of bathroom vinyl flooring. Which is correct? A. Total should be 60SF of Bathroom Vinyl Flooring (SOI – Amend 0001) 2. The Schedule of Items has no lines for drywall replacement, painting, wood flooring or air clearance. Should those costs be included in the existing line items?

A. While not broken out to reflect those items, your pricing, submitted as a LS, can reflect those cost elements. Pricing should be submitted via items 3 and 9, respectively. 3. The attached wage determination (CO20260012) is a Highway determination with no asbestos worker, drywall finisher or brush painter classifications. Will a Building wage determination be issued?

A. Correct WD, CO20260001 provided/attached. (Amend 0001) 4. The SOW lists a start date of October 30th and the solicitation lists November 1st. Which date applies?
A. Block 10 - Correct dates of Performance are 30 October – 30 December 2026 5. The testing report and SOW identify approximately 25 sq. ft. of friable asbestos-containing window glaze, but we could not find an exterior window count or the approximate location of the affected windows. Could you please provide:
Q. The number of exterior windows requiring glaze removal; and A. There are 10 windows. The square footage is not of the windows themselves but the amount of glaze associated with the total number of windows. Added to SOW, River Springs Office Apartment. (Amend 0001)
Q. The approximate side/elevation or location of each affected window. A. The windows are all reachable by a standard folding ladder and the tops of the windows are not more than 10 feet from the ground, possibly not more than 8 feet. There are 4 windows on the front of the building and 2 on each of the remaining 3 sides. The building is a single level and quite small. Added to SOW, River Springs Office Apartment (Amend 0001) 6. Two items are numbered 8 (Kitchen/Dining Room/Bedroom #1 and #2 Drywall Walls and Ceilings, 1000; Bathroom Drywalls and Ceilings, 250), and there is no Item 9. Please confirm that the second is Item 9 and that both are to be priced.
A. Numbering sequence has been corrected to reflect item 9. A revised Schedule of Items will be attached via the amendment. (Amend 0001)
7. Item 1, Mobilization, shows quantity 0 LS. Please confirm how the Government wants it priced.