SUBJECT TITLE:
SITE:
BLDG:
Relocate Air Compressors/ Shed Buildout
US NAVAL RESEARCH LABORATORY (NRL), Washington DC
The statement of work is described below and is comprised of the following sections and attachments. A.
B.
C.
D.
E.
F.
General Contract Information
Technical Criteria
Service
Waste Management
Environment Management System Information
Warranty
A. GENERAL CONTRACT INFORMATION: Provide all services and materials consisting of the following:
o
ATTACHMENT 1
Tasks:
Relocate existing two air compressors in building 65 from mechanical room 026B to outside new metal building.
Provide proper air filtration and automatic condensation removal from air tanks
Extend Siemens BAS wiring system from Room 026B to new compressor location outside. Use Rigid galvanized Conduit for exterior run, Final 24” conduit connection has to be made with flexible metal PVC coated liquid-tight
Extend 3” copper compressed air piping connection from Room 026B to new compressor location outside
Extend compressor power connection from Room 026B to new location outside, use Rigid Galvanized Conduit for exterior run, connect compressor via a 480V heavy duty disconnect switch NEMA 3R. final 24” conduit connection to unit shall be made with flexible metal PVC coated liquid tight.
Provide new 208V-120V panel board in shed to power; lighting fixtures, receptacles, space heater, and exhaust fan. Size panelboard, feeder, branch and conduit per NEC. Provide any additional power/voltage required in the shed to support any added system/ equipment in the shed if needed.
ALL utilities connections shall be above ground from Building 65 to new outside shed.
All penetration to building 65 shall be properly sealed and match existing conditions.
Contractor is responsible for performing any utility ground survey prior to any excavation.
Provide any necessary connections/devices to have a functional working system.
Provide a construction-phasing plan, prior to demolition. One Compressor has to be operational all the time. Air Compressor Outages for relocation is limited to weekends only. An outage request has to be submitted 30 days in
PAGE 1 | 7
advance for review and approval.
•
Metal Shed size: estimated 10’ x 21’ with single sloped roof. Final size by contractor.
•
Concrete slab, 8” @ 4000PSI; of the 8”; 4” has to be below grade and 4” above grade. Provide ½” rebar at 12” OC grid in slab.
•
‘Entry double door; opening space 6’ x 7’; provide galvanized hollow metal doors and frame with louver at bottom. Minimum 1HR fire rated