REMODEL BUILDING 17 HUMAN RESOURCES
Project Number 653-26-110
BACKGROUND:
This project is for Human Resources side of Building 17 on the Roseburg VAMC campus. This project will remodel and upgrade Building 17 Human Resources office space; the ICRA for this project is Level 2. This remodel shall include work with paint, flooring, walls, doors, ceilings and bathrooms. The Contractor shall provide all labor and materials for project management, demolition, and construction services needed to complete this project. All work shall meet SOW, drawings, and specification requirements as well as any applicable manufacturers installation procedures. This project will require a phased construction approach. All measurements, room square footages and quantities are estimated and shall be verified by the contractor. Paint colors to be determined by COR (FYI, VA color codes are on file at the local Sherman Willams for reference).
DESCRIPTION OF WORK
The following items are intended to indicate the general scope of work for the project. The contractor shall complete all work included in the contract documents provided in this solicitation.
Level 4 walls and paint (15447 sq ft)– COR to designate colors Lead paint encapsulation will be required in A113 and A115 (250 sq ft) Demo existing ceiling grid and tiles. Install new 2x2 grid with gasket seal and new tiles (4227 sq ft) Demo carpet and flooring and remove tripping hazard transitions between rooms by making transitions smooth and flat (4102sq ft) Ceiling tiles, carpet, wall base trim and flooring are suspected asbestos containing material, Asbestos abatement will be required Demo wall base trim
Raise flooring in A106 and E122 roughly ½” to remove transition by applying a skim coat self-leveling cement (Basis of design – Custom Building Products TDS-111) Install vinyl flooring in lobby, hallways, offices, and break room. Offices and Halls to be different colors. (4102 sq ft) – COR to designate colors (Basis of Design, Calmness II C2058) Install new 6” vinyl wall base trim – COR to specify
Remodel “A” bathroom – (82 sq ft)
Demo fixtures – Toilets (x2), Urinal, Sinks (x2), repair floor and wall penetrations, Demo piping to nearest junction. Demo floor tiles and wall base tiles
Install new vinyl flooring (Basis of Design – Johnsonite 864) Install new 6” vinyl wall base trim – COR to specify
Demo Dividers
Epoxy walls to existing tile height with colored quartz chips. COR to designate color. (Basis of Design - Blended Quartz Sand - SPARTACOTE)