Statement of Work for Shredder Maintenance

1. Description of Work

Contractor will, in support of USSOCOM, perform shredder maintenance on two Model 1424 SEM Disintegrator Systems and one Model 22 SEM Disintegrator System in accordance with the attached “Shredder Maintenance Technical Requirements”. Regular service is required once per quarter or four times per calendar year. Maintenance will be scheduled no later than 14 days out prior to maintenance. Visits should be scheduled through USSOCOM Engineer Facilities Office. There is a requirement for two categories of unscheduled maintenance, emergency and urgent. Emergency maintenance is required when there is a work stoppage due to breakage. Urgent maintenance refers to maintenance prior to deemed imminent breakage. Contractor must also be able to perform emergency maintenance on an asneeded basis within a 48 hour response period. Contractor must also be able to perform urgent maintenance on an as-needed basis within a 72 hour response period. Contractor is required to clean the shredder area of all debris caused by the maintenance after the maintenance work is completed and before Project Acceptance. A qualified technician is required. Scope may include emergency replacement of parts (to be separately negotiated).

2. Place of Performance

Primary place of performance is building 502, USSOCOM, MacDill AFB, FL.

3. Schedule of Performance

Contractor shall schedule and coordinate quarterly maintenance with the USSOCOM Facilities Office Monday through Friday between the hours of 0700 and 1500. Visits will be scheduled at least 14 working days prior to maintenance. Emergency service will be conducted on an as-needed basis.

4. Security Requirements

Contractor shall be responsible for obtaining a base entry pass in accordance with the base entry requirements. This pass shall be used to gain entry to the base to only perform services to fulfill contractual requirements described in this scope of work. This pass shall not be used to gain entry to any other area of the base.

5. Pay Schedule

Contractor shall maintain the ability to receive electronic payment from the government as stipulated in the contract requirements. This is done through the Wide Area Work Flow system.

6. Reports

Contractor will be required to submit a report after each visit. Report shall address all items identified in the description of work above and the attached checklist.

7. Project Acceptance

Contractor is required to brief the Facilities POC after work is performed and obtain acceptance of