Statement of Work

Project
Removal and Restoration of Gypsum Board
General Information

1.0 Scope of Work

Demolition and installation of a new gypsum board, insulation, and reinstallation of the current A/C unit are needed. Application of antimicrobial agent to floors and all surfaces to eliminate residual microbial presence. We need this removal due to the present mold in the wall and the insulation inside of it. Only cleaning the wall will not resolve the problem, since the evaluation showed the mold and moisture is coming from the inside insulation.

Contractor Requirements

3.0 Technical Requirements / Tasks

1. Safety & Preparation

Certified technician equipped with proper PPE per OSHA regulations. Setup of containment barriers and decontamination chambers to prevent cross-contamination in unaffected areas. Air Filtration Device (Negative Air Fan / Air Scrubber) installed and operated continuously during the project for air purification. Dehumidifier installed to stabilize and control humidity throughout the remediation period. Protective plastic covering applied to isolate work zones and protect unaffected areas.

2. Mold Remediation Procedures

HEPA vacuuming of all affected areas including floors, walls, and ceilings. Use of HEPA filters for canister or backpack vacuums to remove fine particulate contaminants. Application of antimicrobial agent to floors and all surfaces to eliminate residual microbial presence. Air cycling maintained throughout the process to remove contaminated particles from the air.
All equipment setup, monitoring, and takedown performed according to IICRC and OSHA safety standards.

3. Cleaning & Surface Treatment

Light cleaning of all walls and ceilings.
Floor cleaning and antimicrobial treatment as preventive measure. Comprehensive content manipulation and cleaning of furniture, fixtures, and exposed items in affected zones.

4. Construction & Restoration

Demolition and installation of new gypsum board wall in the identified affected area.

4.0 Government Furnished

N/A

5.0 Deliverables / Schedule

Period of Performance: 10 Days after the NTP

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

Describe positions which are considered key to successful performance of the contract and the information required to support key personnel qualifications, e.g., experience which correlates to SOW requirements, education, and past performance on similar projects. Specify if resumes are required and provide resume format if appropriate.