MOD/MODE/US Bypass Canal Repairs Project
SECTION C - DESCRIPTION / SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 12 40
01 14 10
01 14 12
01 14 30
01 33 00
01 35 10
01 35 20
01 35 30
01 51 00
01 55 00
01 55 20
01 56 10
01 57 30
01 74 00
Construction Sequencing
Use of Site
Work Restrictions
Interruption of Service
Submittals
Safety Data Sheets
Safety and Health
Contractor’s Onsite Safety Personnel
Temporary Utilities
Vehicular Access and Parking
Traffic Control
Protection of Existing Installations
Water Pollution Control
Cleaning and Waste Management
DIVISION 31 – EARTHWORK
31 02 10
31 03 10
Water for Dust Abatement
Care of Canal During Construction
END OF CONTENTS
00 01 10 - 1
MOD/MODE/US Bypass Canal Repairs Project
SECTION 01 12 40
CONSTRUCTION SEQUENCING
PART 1
GENERAL
1.01
MEASUREMENT AND PAYMENT
A.
Cost:
1.
Include in prices offered in the Price Schedule for other items of work.
1.02
SUBMITTALS
A.
Submit and integrate the following as part of Construction Plan in accordance with Statement of Work and 01 33 00 – Submittals.
1.03
CONSTRUCTION SEQUENCING
A.
The following work will be conducted by the contractor unless otherwise noted: 1.
BOR to divert flows upstream of MOD, MODE, and US Bypass canals.
2.
Maintain construction areas in dry working conditions.
3.
Demolition/repair of existing, and construction of new concrete canal panels.
4.
Backfill and place concrete lining to match concrete canal adjacent to the repair area.
5.
Joint and crack sealing using Sikaflex product or equivalent.
6.
Handling of accumulated materials, hauling solids for disposal, and submitting completed waste disposal form.
7.
Removal of any temporary berms by Contractor.
8.
BOR put MOD, MODE, and US Bypass canals back in service.
9.
Remaining construction activities that may be accomplished after canal outage.
B.
Contractor to provide a proposed construction sequence to the Contracting Officer’s Representative for approval considering the activities above.
C.
The Government will divert water to the Gila and Colorado Rivers upstream of the work areas before Contractor begins work in the MOD, MODE, and US Bypass canals.
PART 2
PRODUCTS
Not Used
Construction Sequencing
01 12 40 - 1
MOD/MODE/US Bypass Canal Repairs Project
PART 3
EXECUTION
Not Used
END OF SECTION
Construction Sequencing
01 12 40 - 2
MOD/MODE/US Bypass Canal Repairs Project
SECTION 01 14 10
USE OF SITE
PART 1
GENERAL
1.01
MEASUREMENT AND PAYMENT
A.
Cost:
1.
Include in prices offered in the Price Schedule for other items of work.
1.02
REFERENCE STANDARDS
The beginning of the document. Download the full file to read on.