Attachment 4: Statement of Work
Updated
A PDF document (178 KB) attached to Administrative Parking Lot Repairs, from the Forest Service. Due Nov 23, 2026, 2:00 PM (UTC-5).
File name: Attachment 4 - C05 Statement of Work.pdf
The full file is for paid members, or buy this bid alone.
Preview
US Department of Agriculture (USDA)
Statement of Work
Project
Administrative Parking Lot Repairs
General Information
1.0 Scope of Work
This project involves the repair and resurfacing of three parking lots on the Arapaho and Roosevelt National Forest and Pawnee National Grassland including crack sealing, pavement patching, seal coating and re-striping.
2.0 Background
The parking lots have not been re-surfaced or maintained in several years and are showing signs of wear including alligator cracking and horizontal cracking.
The parking lots are located in Fort Collins, CO at the Administrative Site, Idaho Springs, CO at the Clear Creek Ranger District Office and in Boulder CO, at the Boulder Ranger District Office. -
Boulder Ranger District Office
2140 Yarmouth Avenue.
Boulder, CO 80301
-
Clear Creek Ranger District Office
101 CO-103
Idaho Springs, CO 80452
-
Fort Collins Administrative Site
300 Hemlock
Fort Collins, CO 80524
Contractor Requirements
3.0 Technical Requirements / Tasks
The contractor will be responsible for cleaning all surfaces of the parking lots, filling cracks, removing and replacing damaged areas and seal coating the entire surface after the repairs are complete. After seal coating is complete the lots will be restriped. All work must be completed as specified in the included Forest Service Supplementary Specifications (FSSS) and the Federal Highways Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-24.
All the sites will be occupied by Forest Service Employees and the public and will involve strategic closures so that paving operations will have minimal effect on daily operations. Work may be scheduled outside of normal business hours if approved by the Forest Service.
4.0 Government Furnished
There are no Government Furnished items for this project.
5.0 Deliverables / Schedule
•
•
•
Reporting Requirements: The contractor is required to provide written progress reports weekly for the period duration of the project. The progress report shall cover all work completed during the specified period and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation. Submittals: The contractor shall provide submittals for all asphalt products as specified in the supplemental and