JEAN LAFITTE NATIONAL HISTORICAL

PARK AND PRESERVE, CHALMETTE

CEMETERY

REHABILITATE CHALMETTE NATIONAL CEMETERY

140PP027R0004

JELA 325250 335621

REQUEST FOR PROPOSAL

(RFP)
Proposal Submission Package

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

For Technical Volume I:
1.
2.
3.
4.

Experience Questionnaire
Subcontractor Reference
Key Personnel Qualifications
Past Performance Questionnaire

For Business & Price Volume II:
1.
2.
3.
4.
5.

SF 24 Bid Bond
Contract Bid Schedule
General References
Report on Limitation on Subcontracting
Proposed Equals

Project Experience Questionnaire
Solicitation: 140PP027R0004
Submit responses to the questions below that address experience relative to the elements noted under the Project Experience evaluation subfactor in solicitation section L. Limit submittals to the quantity of projects and timeframes required in the solicitation. Expand the response sections shown below as needed to adequately address each question (this questionnaire may be expanded to multiple pages if needed). Offeror

Company Name

Project Title
Project Location
Brief Project
Description
Project Owner

Title
City, State

REFERENCED PROJECT INFORMATION

Description
Company Name

POC:

First & Last Name

Phone:

(XXX) XXX-XXXX

CONTRACTOR LIST

List Contractor(s) whose experience on the referenced project is being submitted for evaluation on this proposed project. If more than one contractor is listed (i.e. prime and subcontractors), provide information specific to that contractor. Performance
Period
Role on
Price
Contractor Name

Referenced
Project

(list for each contractor’s
specific work)

Trade

(Prime or Sub)

Sparky’s Electrical Company

Prime

ABC Plumbing & Heating, Co

Subcontractor

Prime
Plumbing &
Mechanical

(calendar days)
(list for each
contractor’s
specific work)

Original

$XXX,XXX

Final

$X,XXX,XXX

Original
XX

Final
XX

$X,XXX,XXX

$X,XXX,XXX

XXX

XXX

Subcontractor

PROJECT EXPERIENCE QUESTIONS

1. Describe the project work performed by all contractors listed above. Response
2. Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses. Response
3. Describe & provide reasons for any changes to the original price for the work described in question 2 above. Response
4. Describe and provide reasons for any changes to the original schedule for the work described in question 2 above. Response
5. Describe problems, associated with the work described in question 2 above, which were encountered and how they were

The beginning of the document. Download the full file to read on.