127EAX27Q0015
Electrical Updates GCAFB
STATEMENT OF WORK
Electrical Upgrades to the Grant County Aerial Tanker Base & Fire Cache Gila National Forest, New Mexico
Construction Specifications
1. PROJECT OVERVIEW
•
This project consists of furnishing and installing a complete, code-compliant electrical distribution system to support a designated concrete pad area at the Grant County Aerial Fire Tanker Base and Fire Cache, and the upgrade of an existing electrical/motor control panel serving the retardant pumping system
The work includes:
-
The upgrade of an existing electrical/motor control panel serving the retardant pumping system
Extension of electrical service to a designated concrete pad area
The completed system shall be suitable for continuous outdoor service in a high-use industrial environment and designed for durability, safety, and future expansion.
2. APPLICABLE CODES AND STANDARDS
All work shall comply with:
•
NFPA 70 (National Electrical Code – NEC)
•
NFPA 70E (Electrical Safety)
•
NEMA standards
•
UL listing requirements
•
State of New Mexico electrical codes
•
Local Authority Having Jurisdiction (AHJ) requirements
•
USDA Forest Service engineering standards (as applicable)
127EAX27Q0015
Electrical Updates GCAFB
3. GENERAL REQUIREMENTS
The Contractor shall:
•
Furnish all labor, materials, equipment, and supervision
•
Perform a site verification walkdown prior to construction
•
Verify all existing electrical conditions and available capacity
•
Coordinate all work with the Contracting Officer’s Representative (COR)
Installation Quality
•
All materials shall be new, UL-listed, and rated for outdoor use
•
All installations shall be neat, workmanlike, and mechanically secure
Trenching & Surface Restoration
•
Minimize trenching where feasible by utilizing existing infrastructure
•
Restore all disturbed asphalt, concrete, or native surfaces to original condition
4. ELECTRICAL DISTRIBUTION SYSTEM
4.1 Source of Power
All new outlets shall be served from a new service pole, location subject to COR approval.
4.2 Load Design
The Contractor shall:
•
Perform NEC-compliant load calculations (Article 220)
•
Design for:
o
Existing loads
o
New receptacles
o
Minimum 25% spare capacity
4.3 Voltage Drop
•
Maximum:
127EAX27Q0015
Electrical Updates GCAFB
o
3% per branch circuit
o
5% total system
Conductor sizes shall be increased as required.
4.4 Wiring Methods
•
Above ground: EMT or Rigid Metal Conduit (RMC)
•
Underground:
•
o
Schedule 40 PVC (minimum)
o
Schedule 80 PVC at risers
Install pull strings in all conduits