Department of the Air Force: Justification for Other Than Full and Open Competition I. Agency and Contracting Activity (RFO 6.104-1(a)(1)): Agency: ACC
Contracting Activity: 20th Contracting Squadron

II. Nature and/or description of the action being approved (RFO 6.104-1(a)(2)):

This Justification and Approval authorizes the award of a sole source contract to Stanley Drake Construction for the repair and upgrade of electrical power infrastructure in Building 1921 at Shaw Air Force Base, South Carolina. This requirement is necessary to support mission-critical operations directly enabling Operation EPIC FURY within the U.S. Central Command (CENTCOM) Area of Responsibility. The work includes replacement and integration of electrical distribution components, generator systems, transformers, automatic transfer switches, and associated infrastructure required to ensure reliable power to mission systems. The work must be executed within a constrained operational window requiring coordinated outage periods and immediate restoration of full operational capability.

This acquisition will modernize and stabilize the electrical infrastructure supporting Building 1921, a mission-critical facility that enables secure operations, intelligence processing, and command and control functions. The requirement addresses identified deficiencies in system reliability, redundancy, and load capacity that currently limit the facility's ability to sustain continuous operations. These efforts ensure the facility can support current and emerging operational demands associated with Operation EPIC FURY. The work includes integration of new electrical systems with existing infrastructure, coordination with installation utilities, and execution within a tightly controlled outage window to minimize mission disruption.
III. Description of supplies/services required to meet agency needs (RFO 6.104-1(a)(3)):

This acquisition will provide construction services necessary to repair and upgrade electrical power systems supporting Building 1921. The scope includes procurement, installation, and integration of major electrical components such as generators, transformers, switchgear, UPS systems, and associated distribution infrastructure. The requirement also includes coordination of outages, commissioning, and system validation to ensure continuity of mission operations supporting Operation EPIC FURY. The work must be performed in a manner that minimizes disruption to ongoing operations and meets all applicable UFC and installation requirements.