STATEMENT OF OBJECTIVES
D
R
TELECOMM CONDUIT INSTALL
CUSTOMER NAME
129TH RESCUE WING
PROJECT NAME
TELECOMM CONDUIT INSTALL
CIPS REQ#
QMRA-2019-00001
LOCATION
680 MACON RD., MOFFETT ANGB, CA 94035
AUTHOR(S)
THOMAS A. COURCHAINE, MSgt, CA ANG
Telecomm Conduit Install
for the 129th Communications Squadron
Background
The 129th Communications Squadron (129 CS) will be receiving new fiber optic cable infrastructure in support of building 653 that will terminate inside room 21A. However, it has been previously confirmed that additional conduit is necessary to pull the cable into the building and ultimately inside Rm 21A. All work accomplished in accordance with this Statement of Objectives (SOO) shall be performed on behalf of the 129 CS, located at Moffett Air National Guard Base, Santa Clara County CA 94035.
Overall Objective(s)
AF
Technical Objectives
T
The objective of this effort is to engineer, furnish & install (EF&I) a new inside plant (ISP) telecomm conduit that the 129 CS will use to support the future install of a new outside plant (OSP) fiber optic cable (FOC). The primary necessity of this effort is to ensure that an ISP telecomm conduit pathway is already in place and available for use prior to the onset of the forthcoming OSP FOC install inside Rm 21A.
The following information is provided for additional clarification of the aforementioned objective(s).
EF&I one (1) new ISP telecomm conduit in Bldg 653 that extends between rooms 16A & 21A. NOTE: All work to accomplish these objectives will occur at the following approximate location: Lat: 37°24’47.71”N, Long: -122°02’19.39”W.
D
R
Engineering Objectives
EF&I all equipment and material necessary to provide the 129 CS with a new telecomm conduit that includes/retains the same or better specifications and capabilities as those listed below: o
o
o
Material/composite: steel
Length: Approx. 50ft.
Diameter/width: 3in.
The conduit shall be straight without any bends, be one continuous length from end to end, and shall be installed above the existing hard-cap ceiling.
Government Furnished Equipment
There is/will not be any relevant Government Furnished Equipment (GFE) for this project.
Logistics Objectives
The Contractor shall be responsible for the on-site coordination of the install with all applicable third parties and agencies (i.e. Base Civil Engineering & Wing Safety) prior to any work being performed.
The Contractor shall coordinate with 129 CS to gain access to each respective area where work will be