EAR048 - Repair Fire Alarm Systems, Eareckson Air Station Facilities. Industry Questions
Government Response
They are a combination of various systems, most are 25+ year old antiquated conventional 1 Can you provide information about the existing fire alarm system? panels not supported by the manufacturer anymore.
2 What brand is it and would we need to use the same brand for the upgrade? Intend of project is to standardized all systems throughout the area with Monaco systems. Yes. The Government anticipates requiring formal, independently facilitated partnering during For the planned progressive design-build OTA, does the Government design and preconstruction and, if phased construction is authorized, during construction. The anticipate using formal, independently facilitated construction partnering awardee will be responsible for providing and pricing these partnering services as part of during design and preconstruction, and continuing into phased construction agreement performance, consistent with EP 34-1-1, Partnering Playbook (2024). Specific if authorized?
requirements will be included in the solicitation and resulting OTA agreement.
If so, what partnering outcomes or deliverables does the Government expect? Would the Government consider including an independent facilitator in the awardee’s design and pre-construction scope, with funding for continued facilitation addressed in later construction modifications?
The Government anticipates requiring the awardee to provide and price an independent facilitator for partnering during design and preconstruction. If phased construction is authorized, continued partnering facilitation will be addressed in the applicable agreement modification. Expected deliverables may include, but are not limited to, a partnering charter, facilitated workshops, and an issue-resolution process. Specific partnering requirements will be defined in the resulting OTA agreement.
As of 06 NOV 2026