STATEMENT OF WORK
ECAO FACILITY REFRESH – EXTERIOR DOOR REPLACEMENT
1. Project Overview
1.1 Purpose
ft
Replace the 10 exterior door assemblies identified in this SOW and Attachment 5. Include frames when required, hardware, weather seals, and related components. At designated doors, connect new hardware to the existing cardaccess system and automatic operators. All doors must operate safely, resist weather and pest entry, and meet applicable code requirements.
1.2 Work Areas and Required Outcomes
Item
Location
Existing condition
Required finished outcome
Main Building/Main
Level/Primary
Entrance
The existing building’s main
entrance features a set of fulllite, double metal‑framed doors serving as the main entrance.
This door is accessed by card.
Replace the double-door storefront entry.
Include code-compliant hardware integrated
with the existing card reader/security system.
Restore affected surrounding areas.
Main Building/Main
Level/Interior
Vestibule Doors
(See Reference
Photo 2)
Immediately beyond the main
entrance vestibule, a second set
of full-lite, double doors with
metal‑framed provides access
further into the building. No key
card is necessary to access
doors.
Replace the double full-lite vestibule doors
with like-for-like doors and code-compliant
hardware. No card access is required. Restore
affected areas. Follow Attachment 5 for
automatic operator and push-button
requirements.
Main Building/Main
Level/North-Side
Entry Vestibule
Door
Inside the vestibule on the north
side a single‑leaf full-lite door
with a metal frame exists. This is
not used as a daily exit door but
needs to function as an
emergency exit as required. No
key card is necessary to access
door.
Replace the single full-lite door with a like-forlike assembly and code-compliant emergencyegress hardware. No card access is required. Restore affected areas.
Main Building/Main
Level/South‑West
Elevation Door
(See Reference
Photo 4)
A small concrete exterior
stairway along the south‑west
elevation leads up to a single
full-lite door, with a metal frame,
and a solid panel above the
door. This door is accessed by
card.
Replace the single full-lite door and integrate
hardware with the existing card
reader/security system. Restore affected
areas.
D
ra
(See Reference
Photo 1)
Location
Existing condition
Required finished outcome
Main Building/Main
Level/East
Elevation Door
(See Reference