RFP No. 7-B187-P-00016-00
Enclosure No. 3
APPENDIX B – Statement of Work
ANL Industrial Services Contract
November 4, 2026
1.0 Purpose
This Statement of Work (SOW) establishes a Time-and-Materials (T&M) Blanket Purchasing Agreement for industrial services at Argonne National Laboratory (ANL), ordered as needed through individual Call Records or Service Requests. Services include abatement, scaffolding, floor tile removal, window replacement, glazing removal, insulation, and surface preparation and coatings. The qualified Contractor shall provide all labor, materials, equipment, and expertise required for safe, compliant, and high-quality performance.
No work shall involve new construction, expansion, or modification of facilities or systems beyond their original design & function.
2.0 Scope of Services
The Contractor shall provide the following services on an as-ordered basis.
2.1 Insulation Services
• Provide installation, repair, and removal of insulation for piping, ductwork, vessels, tanks, and equipment.
• Utilize insulation materials appropriate to project specifications and operational requirements.
2.2 Abatement Services
• Perform abatement of hazardous materials, including asbestos, lead, and mold, in accordance with all applicable federal, state, and local regulations. • Provide all necessary containment, removal, and clearance testing.
2.3 Scaffolding Services
• Provide engineering and design for scaffolding solutions tailored to project requirements. • Erect and dismantle scaffolding in compliance with OSHA and industry standards.
2.4 Floor Tile Removal
• Remove floor tiles, including asbestos-containing tiles, using approved abatement procedures.
• Provide proper containment, removal, and disposal of asbestos-containing materials.
2.5 Window Replacement
• Remove and replace windows.
• Ensure all installations meet facility and code requirements.
2.6 Window Glazing Removal
• Remove window glazing, including asbestos-containing glazing, using approved abatement procedures.
2.7 Surface Preparation and Coatings
• Prepare surfaces and apply coatings to piping, vessels, tanks, structural steel, floors, and concrete.
• Use industry-approved surface preparation methods (e.g., cleaning, blasting, priming). • Apply coatings in accordance with manufacturer specifications and project requirements. The coating type will be specified per job requirement.
RFP No. 7-B187-P-00016-00
➢
Technical Proposal Requirement: The Contractor shall provide a detailed