Federal Aviation
Administration

Technical Overview of the
Current Data Comm
Program
December 8, 2026

Topics
• Current Status of the Program
– Key Milestones of the Domestic CPDLC Program
– Current Implementation Status
• Tower Services (DCL)
• En Route Services (CPDLC)

•
•
•
•
•

About the DCIS Contract
Protocol, Architecture, and Infrastructure
Use and Performance of Domestic CPDLC
Examples of Problems Encountered
CPDLC Stakeholders and Industry Engagement

Federal Aviation
Administration

Current Status of the Program

Federal Aviation
Administration

Key Milestones of the Program
• 09/2006: Program starts investigating alternatives for restarting Domestic Data Comm • 07/2008: Program gets authority to start the preliminary planning for a selected alternative • 05/2012: Agency commits funding for Tower Services (Departure Clearance) • 09/2012: Data Communications Integrated Services (DCIS) Contract is Awarded • 10/2014: Agency commits funding for the initial set of En Route CPDLC messages (Initial Services)
• 08/2016: Agency commits funding to the remaining set of En Route CPDLC messages (Full Services)
• 08/2022: Strategy Update: En Route Full Services deployment is broken into 3 increments: – Increment 1: messages involving less extensive training, – Increment 2: messages requiring classroom training,
– Increment 3: deferred messages requiring avionics fixes Federal Aviation
Administration

Status S1P1 Implementation
Acquisition Program Baseline (APB) Milestones
ERAM Preliminary Design Review (PDR)

APB Date

Actual Date

September 2011 September 2011

ERAM Critical Design Review (CDR)

March 2012

March 2012

FID: Final Investment Decision for ERAM & TDLS

May 2012

May 2012

DCIS Contract Award

July 2012

September 2012

TDLS Preliminary Design Review (PDR)

December 2012

October 2012

TDLS Critical Design Review (CDR)

August 2013

July 2013

ERAM Initial Test Release (ITR)

June 2014

April 2014

November 2015

March 2015

March 2016

August 2015

December 2016

December 2015

Operational Readiness Decisions (ORD)

April 2017

September 2015

Last-Site IOC

May 2019

December 2016

Operational Test (OT&E)
First-Site Initial Operational Capability (IOC)
In-Service Decision (ISD)

Delivered CPDLC to 55 airports 29 months ahead of schedule and $71.84M million under budget
•
Used some underrun to deliver CPDLC to an additional 7 airports (62 total) •
Used some underrun to upgrade air to ground RF services at 10 airports with enhanced availability / redundancy