MRTS JA Addendum 25169.1 - Redacted
Updated
A PDF document (421 KB) attached to Microwave Radio Test Sets (MRTS), from the Department of the Navy.
File name: MRTS JA Addendum_25169.1_Final - Redacted.pdf
The full file is for paid members, or buy this bid alone.
Preview
UNITED STATES MARINE CORPS
MARINE CORPS SYSTEMS COMMAND
2200 LESTER STREET
QUANTICO VIRGINIA 22134-5050
CT Code: 2.5
J&A Number: 25169.1
ADDENDUM TO JUSTIFICATION AND APPROVAL (J&A)
FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
(Addendum (1))
The purpose of this addendum is to document schedule delays and the resulting revision to the anticipated contract schedule for contract action supported by J&A 25169. Due to command-wide manpower resource assessments, administrative staffing cycles, and a subsequent federal government shutdown in late Fiscal Year 2025 (FY25), contract award was delayed from FY25 to FY26. The schedule delay did not affect the scope of the approved J&A. The Government’s requirement to procure and service the Microwave Radio Test Sets (MRTS) remains unchanged and necessary to support Marine Corps operational requirements. The delay deferred the anticipated start of contract performance and realigned the annual funding profile and four-year ordering period with the revised award schedule. The anticipated 4-year contract ordering period is now expected to occur during FY26-FY30, rather than the previously estimated FY25-FY28 timeframe.
This revised schedule does not change the approved requirement, total estimated value, proposed source, statutory authority, competition approach, or justification for other than full and open competition. The addendum does not authorize contract award or modify the approved J&A. The J&A remains applicable to the anticipated contract action. The following chronology outlines the procurement delay: RFP Planning and Submission (May 2025): Following J&A approval on March 18, 2025, the program office finalized the technical requirements and acquisition planning documents for the Request for Proposal (RFP). The package was submitted to counsel for legal review in May 2025.
Conditional Approval and RFP Release (June 2025): Legal Counsel granted conditional approval of the RFP package in June 2025. The RFP was subsequently issued to Keysight Technologies later that month to obtain their sole-source proposal. Proposal Negotiations (July – August 2025): The Government and Keysight engaged in active negotiations and technical clarifications throughout July and August 2025 to refine pricing, establish technical baselines for the calibrations and repair software, and ensure a fair and reasonable price structure.
Command Workforce Assessment (August 2025): Parallel to negotiations, senior leaders