27 OCTOBER 2026
THIS IS THE MILITARY SEALIFT COMMAND, STRATEGIC SEALIFT PROGRAM
MANAGEMENT SUPPORT OFFICE, NORFOLK, VA, N103A
SOURCES SOUGHT NO. N32205-SS-N103-27-011
SUBJECT: TANKER (LNG) VOYAGE CHARTER
1. THIS IS MARKET RESEARCH CONDUCTED BY THE SEALIFT PROGRAM OFFICE
OF MSC. IT IS A REQUEST FOR INFORMATION ONLY AND YOUR RESPONSE WILL
NOT BE CONSIDERED AN OFFER. THIS REQUEST FOR INFORMATION DOES NOT
COMMIT THE GOVERNMENT TO PAY ANY COSTS INCURRED IN THE
PREPARATION OR SUBMISSION TO THIS SOURCES SOUGHT NOTICE OR TO
CONTRACT FOR SERVICES.
2. MSC REQUESTS INFORMATION ABOUT THE PRICE AND AVAILABILITY OF
U.S. FLAG VESSELS CAPABLE OF CARRYING A MINIMUM OF 50,000 MMBTU
(ABOUT 2,200 CBM) OF LIQUEFIED NATURAL GAS (LNG) TO FILL A STORAGE
REQUIREMENT AT NAVAL STATION GUANTANAMO BAY (NSGB), CUBA. THE
VESSEL IS REQUIRED FOR A CHARTER AS OUTLINED BELOW:
A. MAXIMUM DISPLACEMENT 41,000 METRIC TONS.
B. MAXIMUM LENGTH OVERALL IS 256 METERS.
C. MAXIMUM LADEN DRAFT IS 10 METERS.
D. MAXIMUM BEAM IS 32 METERS.
E. LNG TANKER / BARGE SHALL HAVE A GROSS VOLUMETRIC CAPACITY OF
BETWEEN 4,000 TO 15,000 CUBIC METERS.
F. LNG BARGE/VESSEL PUMP-OUT PRESSURE: 150 PSIG.
G. LNG UNLOADING RATE: 250 CU M/HR.
H. LNG UNLOADING CONNECTION REQUIRED: FLANGED CONNECTION WITH
POWERED EMERGENCY RELEASE COUPLING (PERC) TO 6” LNG HOSE
(PROVIDED BY TERMINAL); EMERGENCY SHUTDOWN (ESD) UMBILICAL.
I. TERMINAL HAS GAS CHROMATOGRAPH TO VERIFY DELIVERED LNG
COMPOSITION AND HHV.
J. MINIMUM LNG SATURATED PRESSURE: 5 PSIG.
K. MAXIMUM LNG SATURATED PRESSURE: 20 PSIG.
L. AVERAGE LNG SATURATED PRESSURE: 10 PSIG.
M. CARRIER SHALL PERFORM THEIR OWN MOORING ANALYSIS. CARRIER
SHALL MEET, AT A MINIMUM, THE REQUIREMENTS IN UFC 4-159-03
MOORING SERVICE TYPE I (35 KNOTS SUSTAINED WINDS, 1 KNOT
CURRENT).
3. CARGO SPECIFICS: 50,000 MMBTU OF LNG (ABOUT 2,200 CBM).
SPECIAL HANDLING AND DISCHARGE REQUIREMENTS: DISCH TERMS 250
CBM PER HOUR, DAYLIGHT ONLY, WWD SHEX. CARGO WILL BE DISCHARGED
FROM SHIP/BARGE TO NSGB PIER C. THIS IS THE FIRST LNG DELIVERY TO
THIS NEW TERMINAL AND THE PURPOSE OF THIS DELIVERY IS TO COMPLETE
THE PROCESS OF COOLDOWN OF THE LNG TERMINAL AND STORAGE TANKS. LNG CRYOGENIC HANDLING AND CONTROLLED OFFLOADING.
4. LOADING PORT: AT CHARTER’S DISCRETION
5. DISCHARGING PORT: NAVAL BASE, GUANTANAMO BAY, CUBA
6. LAYDAY(S): RESPONDENTS ARE REQUESTED TO INDICATE IF VESSEL CAN
MEET THE BELOW DELIVERY DATES:
09-10 NOVEMBER 2026
12-14 NOVEMBER 2026
30 NOVEMBER 2026 – 04 DECEMBER 2026
21-24 DECEMBER 2026
7. INTERESTED PARTIES ARE REQUESTED TO PROVIDE THE FOLLOWING
The beginning of the document. Download the full file to read on.