DC500465_01400_A15 A35 Flooring
and Paint
Naval Air Weapons Station
China Lake, California

Part 1
Proposal Forms & Documents

DC500465_01400_A15 A35 Flooring
and Paint
Naval Air Weapons Station
China Lake, California

Part 2
General Requirements

A15 A35 Flooring and Paint

Naval Air Weapons Station, China Lake, California

DC500465

China Lake SAP Contract
Part 2 General Requirements

PART 2

GENERAL REQUIREMENTS

•

00 00 00 GENERAL REQUIREMENTS

•

01 11 00 SUMMARY OF WORK

•

01 14 00 WORK RESTRICTIONS

•

01 20 00 PRICE AND PAYMENT PROCEDURES

•

01 30 00 ADMINISTRATIVE REQUIREMENTS

•

01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

•

01 33 00 SUBMITTAL PROCEDURES

•

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

•

01 45 00 QUALITY CONTROL

•

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

•

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

•

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

00 00 00 GENERAL REQUIREMENTS

1.1 Definitions

As used throughout the contract, the following terms have the meaning set forth below: The terms “contract” and “Order” are synonymous.
Contracting Officer (KO): The individual designated to administer the contract. Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.
Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.
Contract: Contract or task order.
Contractor (KTR): The term Contractor refers to both the prime Contractor and all subcontractors, whether in contract with the Prime Contractor or other subcontractors at any tier, including the Designer of Record.

PART 2 GENERAL REQUIREMENTS

ver 2025.11

A15 A35 Flooring and Paint

Naval Air Weapons Station, China Lake, California

DC500465

Designer of Record (DOR): Licensed architect/engineer working as subcontractor to or partner with prime Contractor who provides design for this contract.
Engineer Technician (ET): The CORs field representative which will handle the day–to-day activities on the project.
Quality Control (QC): Contractor's system to control the quality of design, material, equipment and construction.
Quality Assurance (QA) Program: Government's program to evaluate the effectiveness of the Contractor's

The beginning of the document. Download the full file to read on.