Performance Work Statement (PWS)
B170 Unit 3K Shower Room Epoxy Repair
Fort Roots NLR Medical Center
Central Arkansas Veterans Healthcare System (CAVHS)
North Little Rock, AR
A. Background: The epoxy coating around the grab bars in the North Little Rock Fort Roots Healthcare Center 3K-116 shower room is starting to peel. The bars themselves have also been deemed non-compliant with the Americans with Disabilities Act (ADA) and require total removal. To replace the Ligature Resistant Grab Bar, the walls will have to be recoated with a matching epoxy color.
B. Scope: Contractor shall provide all tools, shipping, delivery, personnel, transportation, demolition, to recoat the shower section of walls from the left corner around room 3K-116 at the Eugene J. Towbin Healthcare Center.

1. General Requirements

1.1 Task Requirements

• The Contractor shall recoat the wall section of the shower area, from the left corner to the sink, with an epoxy coating that matches the existing color.

1.2 Responsibilities of the Contractors

• Installing the ICRA barrier
• Maintain compliance with all ICRA policies and procedures • Ensure work complies with VA Specs 09 96 59 for Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU • Contractors shall keep all the tools and equipment in their line of sight when entering the medical center
• Keep the patient shower door always locked
• Ensure no patients enter or exit Unit 3K
• Store equipment in the shower room laundry area
• Perform final clean-up of the area before leaving the site • Ensure drains are not clogged with epoxy material

1.3 Responsibilities of the Government

• Provide access to the 3K Unit
• Provide Escort if necessary

1.4 Safety and Environmental Protection

• Comply with all OSHA, EPA, and local safety regulations • Ensure protection of personnel, equipment, and facility operations • Handle and dispose of any hazardous materials per regulations

1.5 Exclusions

• The inward walls surrounding the one recessed window

2. Layout and Pictures

Figure 1. RM 3K-116 Drawing

Figure 2. Main Shower Area
C. Delivery Hours: All deliveries shall be scheduled 48 hours in advance. Deliveries pertaining to this contract will need to be performed Monday through Friday unless a Federal holiday falls on one of these days. Typical hours are between 8am and 4pm. If delivery is required outside of these hours of operations, it must be coordinated with the project Contracting

Officer’s Representative (COR). On the days listed below delivery shall not be scheduled