Performance Work Statement
Remediation, Gasoline Underground Storage Tank (UST) Site, Former Putah Creek
November 13, 2026
1.0 General Description
This is a non-personal services contract to remediate contaminated soil and groundwater at the Former Putah Creek Resort (Site) located at 7600 Knoxville Road in Napa County, California. The Government shall not exercise any supervision or control over the contract service providers (i.e. subcontractors) performing the services. Such contract service providers shall be accountable solely to the Contractor who, in turn, is accountable to the Government.
2.0 Background
A Corrective Action Plan (CAP, Att. 1) was prepared under purchase order R15PX00826 and approved by the Central Valley Regional Water Quality Control Board (CVRWQCB).
3.0 Period of Performance
Base Year
Option Year 1
Option Year 2
Option Year 3
Option Year 4
March 15, 2027, to March 14, 2028
March 15, 2028, to March 14, 2029
March 15, 2029, to March 14, 2030
March 15, 2030, to March 14, 2031
March 15, 2031, to March 14, 2032
This project will be for 5 years, and has a base period of 1 year, with four, 1-year, option years. Option years will be exercised as needed to accomplish the remediation efforts and site closure. 4.0 Government Furnished Property, Equipment, and Services: NONE
5.0 Contractor Furnished Items and Services
The Contractor shall provide all equipment, supplies, management, supervision, personnel, and transportation except as specified herein as government-furnished, necessary to assure that all services are in accordance with the contract and all applicable laws and regulations. The contractor shall ensure all work meets performance standards specified in this Performance Work Statement (PWS).
6.0 Site Access
The Contractor shall allow subcontractors access to the Site for work on groundwater monitoring and remediation as required by Technical Reporting Order, aka Monitoring and Reporting Order (MRP) R5-2012-0800 (Att. 2), pursuant to Cleanup and Abatement Order R5-2009-0704 (Att. 3). The Contractor shall carry out all future groundwater monitoring and remediation work at the Site.
There will be development activities taking place by Park Concessionaires in the vicinity of the Site. The Concessionaire must be allowed access to the existing concrete pad and the Above ground Storage Tank (AST) for fuel vending and storage. Ongoing coordination between the Contractor, Reclamation, and Concessionaire shall be provided to ensure fuel distribution