Performance Work Statement (PWS)
WT 12895002
Bridge Redundant Power from Generator
Supply to Panel RP15 in Building 1470
Peterson Space Force Base (PSFB)
Colorado
19 October 2026
Mr. Timothy Ahlers 554-6721
Mr. Jeff Simon, 554-4992
1.
INTRODUCTION
1.1.
The Contractor shall establish a redundant power infrastructure to support a communications terminal. Primary power will be delivered from the currently installed generator in Building 1471, with secondary redundant power sourced from the Power Distribution Unit (PDU) located in Building 1470, Room 126. To support this terminal, the contractor must run dedicated electrical feeds approximately 100 feet from the PDU in Room 126 to Electrical Panel RP15 located in building 1470 hallway. The installation must deliver the following dedicated circuits to the terminal's breakers: Two (2) x 20-Amp (A) circuits and One (1) x 30-Amp (A) circuit.
1.2.
The Contractor shall provide all labor, materials, equipment, and resources necessary to complete the installation of power run from Building 1470 Room 126 to Electrical Panel RP15 and existing red PDU at Peterson Space Force Base, Colorado, as defined in this Performance Work Statement (PWS). All work must comply with applicable federal, state, and local regulations, including Occupational Safety and Health Administration (OSHA), Unified Facilities Criteria (UFC) 3-520-01-Interior Electrical Systems, National Electrical Code (NEC), National Fire Protection Association (NFPA) 70 and 70E, Peterson SFB Design Guide and manufacturer standards.
2.
GENERAL REQUIREMENTS
2.1.
The Contractor is responsible to verify site conditions, measurements, quantities, and materials needed to complete this project prior to submitting a proposal.
2.2.
Estimated Performance Time: 105 calendar days. This includes 60 days for site survey, planning, coordination, and procurement, and 30 days for labor.
2.3.
All work accomplished by the Contractor shall comply with the contract criteria unless a waiver is obtained from the Air Force when conditions warrant such consideration. All construction work shall be subject to stoppages and delays due to critical PSFB mission requirements. WT 12895002
Bridge Redundant Power from Generator Supply to
SMART-T in Building 1471
2.4.
The Contractor shall, within five days after the Notice to Proceed (NTP) (or timeframe determined by the Contracting Officer), submit a practicable electronic work schedule for approval. This schedule should detail the order of work, anticipated start and completion dates for key tasks, and be