National Aeronautics
and Space Administration
NASA Shared Services Center
Stennis Space Center, MS 39529-6000
11/11/2026
SUBJECT: Request for Quotation (RFQ) 80NSSC27949171Q, Aluminum Alloy Raw Materials This solicitation includes the following sections:
1. Statement of Work/Bid Schedule – Section 1
2. Instructions to Offerors – Section 2
3. Solicitation Provisions/Representations and Certifications – Section 3 4. Clauses/Terms and Conditions – Section 4
5. Quote Evaluation Criteria – Section 5

V14 NOV 2026

SECTION 1

STATEMENT OF WORK/BID SCHEDULE

ENTER SOW/BID SCHEDULE:

V14 NOV 2026

Initial

Aluminum Raw Material Procurement SOW
3. Material meets the dimensional requirements of Section 4.5.

4. A CMTR is provided for each heat or lot and shows conformance to the applicable specification. 5. A CoC is provided for each shipment.
6. Heat or lot traceability is maintained between the material markings and the certifications. 7. No damage or nonconformance is found during receipt inspection.

9.4

Rejection and Rework

If delivered material fails to meet the acceptance criteria defined in Section 9.3: 1. NASA shall provide written notification to the Contractor identify ing the specific nonconfor­ mance(s) within the acceptance timeline defined in Section 9.2. 2. The Contractor shall replace the nonconforming material with compliant material within a mutually agreed-upon schedule, at no additional cost to NASA. 3. Replacement material shall be subject to the same acceptance process defined in Sections 9.1 through 9.3.
4. Shipping costs for return of nonconforming material and delivery of replacement material shall be borne by the Contractor.
5. Rejection of one shipment shall not affect acceptance of other conforming shipments.

9.5

Conditional Acceptance

NASA may, at its sole discretion, conditionally accept material with minor nonconformances (e.g., documentation discrepancies) that do not affect material properties, temper, usability, or domestic origin, provided the Contractor commits in writing to a corrective action plan with a defined schedule. Conditional acceptance shall not relieve the Contractor of the obligation to correct identified nonconformances.

10.0

Period of Performance (POP)

December 1, 2026 through January 31, 2026

11.0

Shipping

The Contractor shall ship all deliverables to:
Marshall Space Flight
Center Shipping/Receiving
Apollo R d., Building 4705
Huntsville, AL 35812

SECTION 2

INSTRUCTION TO OFFERORS

☒52.212-1 Instructions to Offerors – Commercial Products and Commerical Services. (APR