Seal and Stripe Parking Lots
528A5-27-504
Canandaigua VAMC
Specifications
06-01-2026
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and
infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations,
including demolition and removal of existing structures, and
furnish labor and materials and perform work for the Steal and Stripe Parking Lots project as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment
with the Medical Center Engineering Officer
C. Before placement and installation of work subject to tests by
testing laboratory retained by Department of Veterans Affairs,
the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time
for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
D. All employees of general contractor and subcontractors shall
comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes general
roads, parking lots, and site to perform repairs, sealing and striping.
01 00 00 -1
06-01-2026
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website
where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative
security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all
sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project
site without appropriate badge.
They may also be subject to
inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one
week’s notice to the Contracting Officer for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written
permission of the Contracting Officer. Patients and staff are
The beginning of the document. Download the full file to read on.