STATEMENT OF WORK
New York VA OIG Space - Flooring Replacement, Cove Base Replacement, and Wall Painting Project Number: 630SI3167B14
1. Background
The Department of Veterans Affairs requires renovation of selected rooms within the New York VA OIG Space. The work includes removal and replacement of existing flooring, replacement of cove base, and repainting of walls in the scoped spaces. The work shall be performed in a professional manner, coordinated with VA staff, and completed with minimal disruption to building operations.
2. Objective
The objective of this project is to refresh and improve the finish condition of the OIG office space by installing new flooring, new cove base, and new wall paint finishes in the approved work areas.
3. Scope Areas
Included spaces: Offices 201-P, 203-P, 205-P, 206-P, 207-P, 208-P, 211-P; Reception 215-P; Foyer; Entire Hall area; 205A-P and Open Office Area - Shared 204-P. Excluded spaces: Electric Rooms 210-PA and 210-P; Janitor Rooms 226-P and 227-P; Secure Storage Rooms 202-P. No flooring, cove base, or painting work shall be performed in the excluded rooms unless separately directed in writing by the VA.
4. Estimated Quantities
The following quantities are for estimating only. The contractor shall field verify all measurements and existing conditions prior to ordering materials or starting work. No.
Space
Room No.
Flooring SF
Cove Base LF
Total Wall Area SF
Shoji White SF
Slate Blue Accent SF
Office
201-P
161.00
48.3
Office
203-P
160.74
48.5
Open Office Area - Shared
204-P
282.74
64.3
Office
205-P
158.68
47.7
Office
206-P
158.68
47.9
Office
207-P
232.13
58.0
Office
208-P
228.76
61.6
Storage
209-9
- - Office
211-P
162.47
55.3
Foyer
- Hall Area
- 1120
1120
Secure Storage
205A-P
104.77
Reception
215-P
164.52
48.3
TOTAL
2,241.49
666.9
5,585
4,587
Contractor shall field verify all dimensions.
5. Contractor Responsibilities
5.1 Pre-Construction Coordination and Submittals
Attend a pre-construction meeting with VA representatives before starting work. Field verify all room dimensions, wall areas, flooring quantities, cove base lengths, existing conditions, substrate conditions, and site access requirements. Submit product data, color samples, and manufacturer installation instructions for new flooring, cove base, adhesives, primers, and paints for VA approval prior to installation.