STATEMENT OF WORK (SOW)

FOR

U.S. COAST GUARD SECTOR COLUMBIA RIVER

TRASH REMOVAL

1.0 GENERAL

1.1 SCOPE

The contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to perform to the standards in this Statement of Work (SOW). Any questions regarding this SOW must be directed to the Contracting Officer assigned to this contract.

2.0 SPECIFIC REQUIREMENTS/TASKS

2.1 TASK ONE.
2.1.1 Provide 2 5-yard recycling dumpsters and empty 1 time per week. 2.2 TASK TWO.
2.2.1 Provide 1 3-yard dumpster and empty 2 times per week. 2.3 TASK THREE.
2.3.1 Provide 2 4-yard dumpsters and empty 2 times per week.

3.0 CONTRACTOR PERSONNEL

The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.

3.1 QUALIFIED PERSONNEL

The Contractor must provide qualified personnel to perform all requirements specified in this SOW.

3.2 CONTINUITY OF SUPPORT

The Contractor must ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.

3.3 PROJECT MANAGER

The Contractor must provide a Project Manager who must be responsible for all Contractor work performed under this SOW. The Project Manager must be a single point of contact for the Contracting Officer and the COR. The name of the Project Manager, and the name(s) of any alternate(s) who must act for the Contractor in the absence of the Project Manager, must be

provided to the Government as part of the Contractor's proposal. The Project Manager is further designated as Key by the Government. During any absence of the Project Manager, only one alternate must have full authority to act for the Contractor on all matters relating to work performed under this contract. The Project Manager and all designated alternates must be able to read, write, speak and understand English. Additionally, the Contractor must not replace