Statement of Work (SOW)
654-27-130 Eliminate Trip Hazards Facility Wide
VA Sierra Nevada Health Care System
975 Kirman Avenue, Reno, NV, 89502
Date: 10/28/2026
R
AF
T
1. GENERAL
1.1. This project will be located at the VA Sierra Nevada Health Care System facility located at 975 Kirman Avenue, Reno, NV, 89502.
1.2. The purpose of this document is to detail a design-build project to be performed by the contractor to develop a solution to survey and remediate the flag circle, Emergency Department (ED) and Community Living Center (CLC) parking lots, sidewalks, curbs, landscaping, signage, wheel stops and several driveways in the facility that have sustained damage, eliminating trips and fall hazards.
1.3. The Design Build (DB) contractor must furnish:
1.3.1. Design: all design Architect Engineer (AE) services, equipment, materials, supplies, investigations and project supervision, and construction period services associated with this contract. Design must meet Veterans Affairs Design Guides and Design Criteria and Veterans Affairs Master Specifications at the technical information library TIL (www.cfm.va.gov/TIL). Design must follow all current applicable codes. 1.3.2. Contractor shall provide all the equipment, labor, materials, tools and supplies required for construction of the project in accordance with the drawings and specifications.
1.3.3. The Design Build contractor will be responsible for providing a complete set of construction specifications along with design drawings, engineering calculations for this project
D
2. SCOPE
2.1. The scope of this project is to detail a design-build project to be performed by the contractor to repave the flag circle located off Locust Street, the ED parking lot located on the corner of Locust Street and Burns Street, and the CLC parking lots off of Locust Street and Taylor Street. Project will also include a facility wide site survey to assess exterior stairways, crosswalks, damaged parking lots, wheel stops, driveways, sidewalks and curbs on VA and city of Reno property. Damage found from the site survey will be repaired as part of the project. Landscape buffers will be landscaped to meet city of reno landscaping requirements. This will include the addition of brick pavers to the west side of campus in place of asphalt that was previously located on the road verge next to the sidewalk. 2.2. The proposal shall be prepared to reflect all work required to provide a complete and functioning system.
2.3. Design-Build team to perform evaluation of existing conditions and work with the facility to
The beginning of the document. Download the full file to read on.