Statement of Work
Pavement Preservation
Tamarac National Wildlife Refuge
Entrance Road and Parking
Revised: 7/16/2026

U.S. Fish and Wildlife Service
Midwest Region – Region 3

Point of Contact - The U.S. Fish and Wildlife Service Point of Contact for this requirement is: Alisha Haken
Deputy Project Leader
Tamarac National Wildlife Refuge, 35704 County Highway 26, Rochert, MN 56578 218-308-7161 (office)
218-849-9867 (cell)
[email protected]

Brandon Jutz (secondary)
Regional Transportation Coordinator
Bloomington, MN
612-713-5407 (office)
571-305-0188 (cell)
[email protected]

Statement of Work – This Statement of Work describes the general performance of the completed project and does not attempt to show the exact construction of the work in complete detail. Provide high-quality completed work that maintains the performance intent established by this document. Project Location – The project location is the Entrance Road and Visitor Center Parking (Route #900) at the Tamarac National Wildlife Refuge. The Refuge address is 35704 County Highway 26, Rochert, MN 56578.

Project Overview – The U.S. Fish and Wildlife Service (FWS) needs the Contractor to apply crack sealing and slurry seal to the Entrance Road and Visitor Center Parking in order to protect and preserve the condition of the pavement and extend the service life of the pavement.

Project Description –

Route
Number
Route
Name
Route
Length
(mi)
Route
Width
(FT)
Surface
Area (SY)
Specified
Treatment
Visitor Center Pkg
-- -- 4,826
Crack sealing1
Patching2
Slurry seal3
Pavement markings4
1 Reference construction specifications for Crack Sealant within SECTION 321216 – ASPHALT PAVING 2 Reference construction specifications for Patching within SECTION 321216 – ASPHALT PAVING 3 Reference construction specifications for Slurry Seal within SECTION 321216 – ASPHALT PAVING 4 Reference construction specifications for Pavement Markings within SECTION 321723 – PAVEMENT MARKINGS Period of Performance -

Start Date: upon issuance of the Notice to Proceed
Completion Date: 90 days after issuance of Notice to Proceed

Work must be performed between 6:00 a.m. and 6:00 p.m., Monday through Friday. No work is allowed on Federal holidays. Ideally, work would take place on a Monday and Tuesday, as the facility is closed to the public and would limit traffic and reduce traffic control issues.

Temporary Traffic Contral - Develop a traffic control plan to ensure contractor and public safety during construction operations.