Statement of Work (SOW)
Kooskia National Fish Hatchery – Rain Gutter Replacement Project

1. Project Overview

Kooskia National Fish Hatchery is looking for contractors to replace existing rain gutters and downspouts. This project includes installing new 5" gutters and four 20-foot downspouts (approx.) on each building listed below. The contractor shall provide all labor, materials, equipment, and supervision necessary to complete this project.
•

Incubation Building – ~190 linear feet, four 20’ downspouts (approximately)

•

Reuse Building – ~160 linear feet, four 20’ downspouts (approximately)

•

Maintenance/Vehicle Storage Building – ~260 linear feet, four 20’ downspouts (approximately)

•

Chiller Building – ~160 linear feet, four 20’ downspouts (approximately)

All listed measurements are approximate. Contractors must conduct an on-site inspection to verify all measurements and conditions before submitting a bid. The attached visual reference KNFH RAIN GUTTER IMAGE shall be used for general context only and does not represent final measurements or structural details

2. Scope of Work

•

Remove and properly dispose of existing gutters and downspouts.

•

Provide and install new 5” gutter systems sized appropriately for each building’s roofline.

•

Install four 5” downspouts per building (approx. 20 feet each).

•

Ensure gutter systems meet all applicable federal, state, and local codes.

•

Ensure all materials and installation methods follow industry standards.

•

Restore work areas to original condition after installation.

3. Site Visit Requirement

Contractors are required to visit the site prior to bidding. No additional compensation will be granted for discrepancies discovered after contract award.

4. Warranty Requirements

Contractors shall provide the following warranties:

4.1 Material Warranty

•

All gutter materials, downspouts, hangers, and hardware shall be warranted by the manufacturer for defects in material for a minimum of 10 years.

•

Warranty documentation must be provided to the Government upon project completion.

4.2 Workmanship Warranty

•

Contractor shall provide a minimum 2-year workmanship warranty covering installation defects, improper fastening, inadequate slope, leakage due to installation error, and any failure resulting from contractor workmanship.

•

The contractor should correct, at no additional cost to the Government, any deficiencies discovered during the warranty period.

4.3 Warranty Coordination

Given that warranty conflicts can arise when installing new systems onto older structures the

The beginning of the document. Download the full file to read on.

Other documents in this bid