CUI
DESIGN/BUILD
STATEMENT OF WORK
FOR
WATEREE OFFICE CABIN
24 July 2026
PROJECT: VLSB 25-0024
SCOPE OF WORK:
The Design Build Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and nonpersonal services necessary to design and construct a log cabin kit to be ordered from Conestoga Log Cabins. Existing site already has 2 new Conestoga Log Cabins and continuity is recommended.
The Design Build Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and nonpersonal services necessary to design and construct an asphalt paved parking lot for the Wateree Recreation users and employee use. All work shall be done in strict accordance with this Statement of Work and subject to the terms and conditions of the contract and in accordance with Unified Facilities Criteria (UFC), Unified Facilities Guide Specifications(UFGS), International Building Code (IBC), National Electrical Code (NEC), National Electrical Safety Code (NESC), National Fire Protection Association (NFPA), EPA 402-K-01-001 (2008), South Carolina Department of Transportation (SCDOT), and Shaw Air Force Base Design Standards. Additional information is included in the following attachments that must be reviewed:
•
Attachment A: Preliminary Design
BASE BID (CLIN 0001):
•
•
•
•
Demo existing utilities, retain connection point for water, sewer, and power. All will be re-utilized for the new building
Construct new concrete foundation and 12” square masonry piers spaced at 8’ O.C. each way for the main building and 8’ O.C. for the porch ensuing the finished floor elevation is a minimum 2’ above the existing foundation Construct rim joist and girder system on top of the masonry piers. Exterior and interior beams shall be three 2x12’s nailed together with 16d nails, 12” O.C., alternating the length of the beam
o Strap beam to masonry piers
Procure and install the log cabin from Conestoga
VLSB 25 - 0024
CUI
CUI
•
o Ensure the structural requirements are met for uplift Install wood stairs and ramp meeting ADA requirements
o Install appropriate foundation and posts to accommodate the new stairs and ramp
SITEWORK:
•
•
•
•
•
Prepare the existing site by thoroughly compacting the subgrade before starting construction
Grade, pave, and paint a parking lot in front of proposed office for users and handicap accessibility. Provide the necessary Handicap spot and meet all