Move SSERVI Regolith Testbeds at NASA Ames Research Center
STATEMENT OF WORK
1. Objective/Requirements
1.1. Support the relocation of three SSERVI regolith simulant testbeds from Building 503 to Building 267A at NASA Ames Research Center. The three testbeds are described below and are named for identification throughout this SOW:
a) Highlands Testbed (HT) – measures approximately 62’x13’x1’ and contains approximately 22 tons of anorthosite regolith simulant called LHS-2E (SDS attached) b) Lowlands Testbed (LT) - measures approximately 13’x13’x1.5’ and contains approximately 8 tons of basaltic regolith simulant called JSC-1A (SDS attached) c) Deep Testbed (DT) - measures exactly the same as the current container (approximately 18’ x 5’ x 5‘) and contains approximately 12 tons of anorthosite (SDS attached)
Tasks required for these moves are:
•
Move the HT testbed from M503 to N267A
o Build a new HT in N267A prior to moving the regolith
o HT should:
▪ Measure 62’x13’x1’
▪ Provide a continuous heavy-duty, commercial/industrial-grade covering for the inside of testbed frame. Material shall be black with a matte / flat, non-reflective finish. Glossy or visibly reflective finishes are not acceptable.
▪ Top and outside surfaces of the testbed frame should be painted flat black o Collect, package and transport LHS-2E regolith simulant from M503 to N267A abiding by all applicable safety regulations and guidelines • Move the LT testbed from M503 to N267
o Build a new LT in N267 prior to moving the regolith
o LT should:
▪ Measure 13’x13’x1.5’
▪ Entire testbed frame should be painted flat black
o Collect, package and transport JSC-1A regolith simulant from M503 to N267A • Move the DT testbed from M503 to N267 Shed
o DT should:
▪ Be emptied of regolith simulant in N503 and bagged for transport.
▪
▪
The existing testbed frame measuring 18’ x 5’ x 5‘ and including platform for the users to stand on should be moved to the N267 Welding Shed. Packaged regolith simulant should be transported and bags deposited in the same facility. Note bags do not need to be emptied once moved to the new facility.
1.2. The Contractor is responsible for developing a site-specific safety plan and all other required submittals necessary to safely relocate the SSERVI Regolith Testbeds. All submittals shall be prepared in accordance with applicable Fed-OSHA and NASA Ames requirements. The Contractor shall submit all required submittals to the Government for review and concurrence
The beginning of the document. Download the full file to read on.