Specifications
1.0 Introduction/Background: This Specifications Document defines the technical requirements for the procurement of custom hermetically sealed fiber-optic assemblies manufactured in accordance with NASA’s configuration needs. These assemblies are required to support mission-critical applications that demand vacuum compatibility, precise optical performance, hermetic sealing, and specialized materials not available in standard commercial fiber products. The following specifications are derived from the supplier’s formal quotation and reflect the exact configuration required for successful integration into NASA systems.

1. Part Configuration

a. Item Type: Custom fiber assembly per customer specification, Part Number FFH05026-CUSTOM
b. Quantity Configurations:
i. 20 units at 5 m length
ii. 40 units at 1 m length

2. Fiber Characteristics

a. Fiber Type: FFH05026
b. Length Requirements:
i. 5 m ± 20 cm (first configuration)
ii. 1 m ± 20 cm (second configuration)

3. Mechanical Construction

a. Jacket: Hermetically Sealed Stainless-Steel Microtube, internal structure

FT052SSB‑SABR

b. Unit Net Weight: 0.0004 kg per assembly
c. Country of Origin: USA

4. End Terminations

a. End A: Special Order Hermetic SMA connector
b. End B: Special Order Hermetic SMA connector
i. (These are not catalog-standard and must be manufactured per specification.)

5. Materials and Environmental Requirements

a. All assemblies must be built using vacuum-compatible epoxies equivalent to catalog MFV1L1, ensuring performance in vacuum or controlled environments.
b. Components must meet or exceed the quoted specifications; assemblies must include a certificate of conformance (generic) with delivery.

6. Production and Delivery Requirements

a. Lead Time:
i. 10 weeks ARO for the first 5 units of either configuration ii. 5 units per week thereafter
iii. Total completion at 22 weeks ARO for the full 60-unit order b. All items are custom and non‑cancelable once ordered.

7. Compliance Requirements

a. Vendor must comply with US, UK, and EU export laws; diversion contrary to regulations is prohibited.
b. Title transfers at point of shipment from supplier’s facility. Place of Delivery:
NASA Langley Research Center
Mail Stop MAIL STOP 061
Hampton, VA 23681-2199