Preview
Replace Domestic/Chilled Water, Steam Piping
Durham VA Health Care Systems
Bid Documents Specifications
Project No. 558-24-160
1/21/2025
Above Group, Inc.
305 East Dr. Suite H
Melbourne, FL 32904
(321) 345-9026
www.abovegroupinc.com
Department of Veterans Affairs
Durham VA Health Care Systems
508 Fulton Street
Durham, NC 27705
06-01-24
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
SECTION NO
DIVISION AND SECTION TITLES
DATE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00
01 33 23
01 35 26
01 42 19
01 45 00
01 45 29
01 57 19
01 58 16
01 74 19
01 81 13
01 91 00
General Requirements
Shop Drawings, Product Data, and Samples
Safety Requirements for Major Projects
Reference Standards
Quality Control
Testing Laboratory Services
Temporary Environmental Controls
Temporary Interior Signage
Construction Waste Management
Sustainable Construction Requirements
General Commissioning Requirements
11-21
11-23
05-24
11-20
02-21
11-18
01-21
07-15
04-22
10-17
04-22
DIVISION 02 – EXISTING CONDITIONS
02 82 13.13
Glovebag Asbestos Abatement
01-21
DIVISION 09 – FINISHES
09 22 16
09 29 00
09 51 00
Non-Structural Metal Framing
Gypsum Board
Acoustical Ceilings
06-18
04-20
12-18
09 91 00
Painting
01-21
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41
Seismic Restraint Requirements for Non-Structural Components
01-21
DIVISION 22 – PLUMBING
22 05 11
22 05 23
22 07 11
22 08 00
22 11 00
Common Work Results for Plumbing
General-Duty Valves for Plumbing Piping
Plumbing Insulation
Commissioning of Plumbing Systems
Facility Water Distribution
01-23
09-20
09-19
11-16
05-21
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11
23 05 12
23 05 41
Common Work Results for HVAC
General Motor Requirements for HVAC and Steam Generation Equipment Noise and Vibration Control for HVAC Piping and Equipment
00 01 10-1
03-23
03-23
03-23
06-01-24
SECTION NO
23 07 11
23 08 00
23 21 13
23 22 13
23 22 23
DIVISION AND SECTION TITLES
HVAC and Boiler Plant Insulation
Commissioning of HVAC Systems
Hydronic Piping
Steam and Condensate Heating Piping
Steam Condensate Pumps
DATE
02-20
03-23
03-23
03-24
04-20
DIVISION 26 – ELECTRICAL
26 05 11
26 05 19
26 05 26
26 05 33
Requirements for Electrical Installations
Low-Voltage Electrical Power Conductors and Cables
Grounding and Bonding for Electrical Systems
Raceway and Boxes for Electrical Systems
APPENDICES:
-
Appendix A: NESHAP Asbestos and Lead Report
The beginning of the document. Download the full file to read on.