Amendment 0001 for Solicitation N4523a27Q5704 – 750kW EDG at PSNS&IMF Questions and Answers
PWS 10.2.2 says delivery within 48 hours of award. Is Nov 20 2026 the required on-site date no matter when award happens?
RDD is 11/20/26. If award happens more than 48 hours earlier, we would like the unit as early as the 18th if contractually possible.
Where exactly at PSNS & IMF does the generator go (building, dry dock, pier), and is a move to another base (PWS 8) expected during the term?
Delivery location within PSNS&IMF Bremerton is at Pier 6. This unit will not be moved to a different base.
The CLINs show 7 base months starting Nov 20 and 5 option months ending Nov 19. Should partial months be priced as full months or prorated, and is billing monthly in arrears through
WAWF?
Price them as full months. When you submit your invoice in WAWF, you will be submitting it at the end of that period for that period.
Is any transfer switch, distribution gear or load bank needed from the contractor, or is the Navy's connection gear all government-furnished (PWS 5.1)?
Connection equipment/cabling is government-furnished.
Do the fuel tests (PWS 4.1.1–4.1.2) cover the fuel delivered in the unit at delivery? No. This should be accomplished prior to delivery. Vendor should test their fuel and ensure it can comply with 4.1.1-4.1.2. PWS 3.1.1.3 and 3.1.1.6 repeat the reverse-power requirement. Can you give the expected use (shore power, caisson or facility) or a target trip setting? Expected use is connection to boat as secondary long-term source in event of loss of primary source from shore.
Will the generator be connected to the ship (USS Alexandria) or to a facility, and can the remotestart and alarm contacts (PWS 3.1.1.7 and 3.1.1.9) be plain dry contacts? Connected to the boat. Unit should comply with 3.1.1.9 through 3.1.1.9.3
Since the work is mostly equipment rental, which SCA labor categories from WD 2015-5525 Rev 32 apply, if any?
While it’s dependent on the worker and their function SCA categories that could apply include things like 05110 - Mobile Equipment Servicer or 31362 - Truckdriver, Medium Is a vendor quote on letterhead plus a spec sheet enough pricing support under solicitation item 19.D?
Yes, this would be sufficient.
Can delivery and pickup be built into the monthly CLIN price, or should they be shown separately?
The CLINs are set up for the total service for each service period. Delivery and pickup may be built into your CLIN pricing