Attachment 1: MACC Construction Experience Sheet
Updated
A Word document (33 KB) attached to NIH Multiple-Award Construction Contract (MACC) for General Construction Services, from the National Institutes of Health. Due Dec 15, 2026, 2:00 PM (UTC-5).
File name: Attachment 1 MACC Construction Experience Sheet.docx
The full file is for paid members, or buy this bid alone.
Preview
ATTACHMENT “1”
CONSTRUCTION EXPERIENCE PROJECT DATA SHEET – OFFEROR
This form is to be completed by the Offeror. Submit (one per project) in order to provide supporting project information for Factor 1, subfactor 3, Construction Experience. Only projects that are within the project description parameters of the solicitation will be considered relevant. Submit total of 4 projects. All other projects will not be considered. A Page 2 can be used if information will not fit in blocks provided below. Project No. (check one): FORMCHECKBOX - 1 FORMCHECKBOX - 2 FORMCHECKBOX - 3 FORMCHECKBOX - 4 Contractor:
1.
Offeror Name:
FORMTEXT
Firm who performed the work:
FORMTEXT
Performed this work as:
FORMCHECKBOX Prime Contractor FORMCHECKBOX Joint Venture FORMCHECKBOX Other (explain):
FORMTEXT
If the firm who performed this project differs from the Offeror proposing on this contract, identify the firm’s relationship to the Offeror: FORMCHECKBOX Joint Venture Partner FORMCHECKBOX Partner FORMCHECKBOX Subsidiary
FORMCHECKBOX Parent Company
FORMCHECKBOX Affiliate
FORMCHECKBOX Predecessor Company
FORMCHECKBOX Other: FORMTEXT
Construction Contract:
2.
Contract/Project No.:
FORMTEXT
Delivery/Task Order Number:
FORMTEXT
Title:
FORMTEXT
Location:
FORMTEXT
Brief Project Description:
3.
Award Date (mm/dd/yy):
FORMTEXT
Award Amount: $
FORMTEXT
Completion Date (mm/dd/yy):
FORMTEXT
Current/Final Amount: $
FORMTEXT
4.
Type of Contract:
FORMCHECKBOX Design-Build. If D-B, design firm was:
FORMTEXT
(check one)
FORMCHECKBOX Design-Bid-Build
Customer:
5.
Name:
FORMTEXT
Point of Contact Name/Title:
FORMTEXT
POC Phone Number:
FORMTEXT
POC Email Address:
FORMTEXT
Project Description:
6. Type of Work (check all that apply): FORMCHECKBOX New Construction FORMCHECKBOX Renovation/Repair 7. Type of Project: (check all that apply):
☐Biomedical Research Laboratory
☐Health Care Facility/Hospital
☐Animal Care Facility
☐Predominantly Utility Project
☐Renovation/Repair
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Bid document
- Attachment 2: Past Performance Information Sheet
- Attachment 3: MACC PAST PERFORMANCE QUESTIONNAIRE for Offeror
- Attachment 6-MACC Small Business Plan
- Attachment 8: General Decision Number 06 04 2026
- Attachment 9: Building 4 Replace AHUs 3 4 and 4A Construction Statement of Work
- Attachment 9a NIH B4 Replace AHUs Specifications
- Attachment 9b NIH B4 Replace AHUs Drawings