Attachment 1: Specifications
Updated
A PDF document (4.1 MB) attached to Rehab Kiosk Restrooms, NPS-ORCA, from the Departmental Offices. Due Nov 16, 2026, 5:00 PM (UTC-8).
File name: B08_Att_01_140PP027Q0018_Specs.pdf
The full file is for paid members, or buy this bid alone.
Preview
OREGON CAVES NATIONAL
MONUMENT & PRESERVE
REHABILITATE KIOSK
RESTROOMS TO IMPROVE VISITOR
ACCESS AND EXPERIENCE
PMIS No. 215914
CONSTRUCTION SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
Specifications - Rehabilitate Kiosk Restrooms, Oregon Caves NM&P
DIVISION 01 – GENERAL REQUIREMENTS
Section 01 10 00 – Summary of Work
PART 1 – GENERAL
ITEM 1 – DESCRIPTION OF WORK
1.1 Background
The existing public restroom facilities are deteriorated, outdated, and non-compliant with current accessibility and sanitation standards. Interior finishes have exceeded their service life and building envelope penetrations have allowed rodent intrusion. Plumbing and electrical systems are obsolete and no longer meet current safety codes. The restroom interiors will be gutted to structural framing, replace mechanical, plumbing, and electrical systems, install sanitary wall finishes, construct fully compliant ADA restroom layouts, and implement permanent rodent exclusion measures in accordance with National Park Service cultural resource protection requirements.
1.2 Work Covered by Contract Documents
The contractor shall furnish all labor, materials, tools, supervision, and incidentals necessary to complete the following work:
A. Interior Demolition
•
Remove all interior finishes to exposed structural framing, including: o
Ceramic wall tile and mortar bed
o
Gypsum board, paneling, and trim
o
Suspended and framed ceiling assemblies
o
Thermal and vapor insulation
•
Remove all plumbing fixtures, piping, valves, and supports
•
Remove all electrical fixtures, devices, wiring, and associated equipment
•
Remove all restroom partitions and accessories
Specifications - Rehabilitate Kiosk Restrooms, Oregon Caves NM&P •
Remove all floor tiles, adhesives, and setting bed to expose structural slab
•
All materials that a removed need to be hauled off site to an approved disposal or recycling center.
All demolition shall comply with OSHA 29 CFR 1926 Subpart T and EPA construction waste handling regulations.
B. Reconstruction
The contractor shall reconstruct the restroom interiors including: •
Installation of new plumbing distribution and vent systems per IPC 2021
•
Installation of new branch electrical circuits and lighting systems per NFPA 70 (NEC)
•
Installation of new sanitary PVC wall and ceiling panel systems
•
•
o
Combined walls and ceilings: 884 SF
o
Wall panels shall overlap top lip of tile cove base and seal to create watertight seam. See section 1.5 concrete floor repair for tile information.
Installation of ADA compliant partitions and fixtures
The beginning of the document. Download the full file to read on.