17416-26-001
SOO No: 17416-26-001
27 October 2026
STATEMENT OF OBJECTIVES (SOO)
FOR
SERVICE AIR SYSTEM REVITALIZATION
1.0 PURPOSE
The purpose of this project is to revitalize a Service Air System at the Arnold Engineering Development Complex (AEDC), located at Arnold Air Force Base, Tennessee. The current service air infrastructure has experienced reduced reliability and capacity due to aging equipment. The goal of this revitalization is to deliver a fully operational, safe, energy-efficient, and modernized compressed air and dry air network. This will be achieved through the engineering, design, procurement, installation, and commissioning of new Ingersoll-Rand (IR) compressed air equipment, alongside the refurbishment and integration of existing system components.
2.0 SCOPE
The scope of this initiative encompasses the engineering, system design, procurement, delivery, installation, integration, refurbishment, and commissioning of new and existing service air assets across three primary facility locations:
• Building 541
• Building 913
• Building 878
This program entails replacing eleven (11) obsolete IR air compressors, replacing one (1) IR desiccant dryer, relocating and reinstalling an existing compressor, refurbishing six (6) existing IR desiccant dryers, and upgrading associated electrical, piping, and condensate management infrastructure.
3.0 BACKGROUND
The Service Air System provides essential compressed air capacity to support facility operations. To maintain this system, several key replacements and system refurbishments are required: • Building 913: Six (6) rotary-screw air compressors require replacement. • Building 878: Four (4) rotary-screw air compressors require replacement. One (1) rotaryscrew compressor was replaced in 2020; it is in good working order but must be relocated and integrated into the new facility layout.
• Building 541: One (1) obsolete centrifugal air compressor (CENTAC) and one (1) associated desiccant dryer require replacement.
• Dryer Revitalization: Six (6) existing Ingersoll-Rand (IR) HB4000 desiccant dryers located in Buildings 913 and 878 require complete refurbishment to restore them to full moistureremoval capacity.
NOT SENSITIVE
IRA-26-2125
17416-26-001
The critical assets involved in this program are outlined below: Current Model Current Serial
Number
Number
HPE300-2S EE2816U08074
HPE300-2S
EE2817U08084
HPE300-2S
EE3262U11101
HPE300-2S
EE3261U11101
HPE300-2S
HPE300-2S
HPE300-2S
HPE300-2S
RS220ie
HPE300-2S
EE3260U11098
The beginning of the document. Download the full file to read on.