8R Mid field RVR and 15L rollout RVR access roads

HAS Project No. TIP-25-112-IAH
Construction Safety and Phasing Plan (CSPP)
George Bush Intercontinental Airport (IAH)

FOD Inspections: Refer to Section 11 for FOD inspection requirements. 9. Hazardous

1. Background

1.1. Project Overview

Build a concrete access road from Runway 8R Mid field RVR to Taxiway CC and a gravel access road from Runway 15L Roll out RVR to the end of Taxiway WP nearest to the RVR.

1.2. Construction Safety Documents

FAA Advisory Circular (AC) 150/5370-2G Operational Safety on Airports during Construction requires implementing procedures to increase safety during construction. The Construction Safety and Phasing Plan (CSPP) is one of two primary tools required to ensure safety compliance during construction. This CSPP was developed concurrently with the project drawings for this project and will be referenced throughout the construction of the project.
The following are general safety objectives that shall be achieved to maximize safety and to minimize time and economic loss to the aviation community, construction contractors, and others directly or indirectly affected by the project. The Contractor shall be responsible for controlling its operations and the operations of subcontractors (at all levels) and suppliers as they comply with the requirements of this document and as listed below: •
•
•
•
•
•
•

Maximize safety of aircraft operations
Keep the airport operational for all users
Provide for aircraft operational safety
Maintain airfield operations within agreed parameters
Minimize delays to aircraft operations
Minimize delays to construction operations
Minimize airport operation and construction activity conflict

The Contractor shall submit a Safety Plan Compliance Document (SPCD) acceptable to the Owner prior to the Notice to Proceed (NTP). The SPCD shall conform to requirements found in AC 150/5370-2G, paragraph 2.4.2.

2. Coordination

Per FAA AC 150/5370-12B, Quality Management for Federally Funded Airport Construction Projects, meetings will be conducted to ensure the Owner, the Engineer, the Contractor, and other interested parties are aware of design, safety, and construction requirements

and have an understanding of their individual responsibilities, as well as the technical and legal requirements of the contract.
A. Pre-Construction Meeting: HAS will conduct a pre-construction meeting prior to issuance of construction Notice to Proceed. Attendees will include the Authority staff,