YELLOWSTONE NATIONAL PARK
WYOMING
BRIDGE PRESERVATION
PMIS 338223
PROJECT SPECIFICATIONS
100% Submittal
September 2026
D
E
LI
19499
Date:
09/18/2026
W
YOMI
NG
)
l
vi
i
(C
O
R
J
gi
lEn
ne
na
e
o
i
N
S
Y
E
r
Prof
es
s
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00
01 26 01
01 27 00
01 31 00
01 32 16
01 32 33
01 33 23
01 35 23
01 40 00
01 50 00
01 57 19.12
01 57 23
01 67 00
01 73 40
01 74 19
01 77 00
Summary of Work
Contract Modification Procedures
Definition of Contract Line Items
Project Management and Coordination
Construction Schedule
Photo Documentation
Submittal Procedures
Safety Requirements
Quality Requirements
Temporary Facilities and Controls
Noise and Acoustics Management
Under-An-Acre Pollution Prevention
Product Requirements
Execution
Construction Waste Management and Disposal
Closeout Procedures
DIVISION 02 - EXISTING CONDITIONS
02 41 00
Selective Demolition
DIVISION 03 - CONCRETE
03 30 00
03 30 10
03 30 20
Concrete
Structural Concrete Repair
Concrete Accessories
DIVISION 04 - MASONRY
04 01 40
Stone Restoration
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 18 01
Modified Concrete Overlay
DIVISION 09 - FINISHES
09 90 00
Painting
DIVISION 31 - EARTHWORK
31 23 10
31 25 00
31 32 19
31 37 00
Excavation and Backfill
Erosion and Sediment Control
Geotextiles
Riprap
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 12 16
32 17 23
32 91 13
32 92 19
Asphalt Paving
Pavement Markings
Topsoiling and Soil Conservation
Seeding and Mulching
DIVISION 34 - TRANSPORTATION
34 20 00
Maintenance of Traffic
APPENDIX
A
B
Size and Weight Limitations
2024 Equipment Inspection Contact List
NPS DSC Division 1 Specifications
YELLOWSTONE NATIONAL PARK – 338223
SECTION 01 10 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1
SUMMARY
A. Section includes the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
1.2
Work Covered by Contract Documents
Work Phases
Work Under Other Contracts
Government-Furnished Materials
Contractor Use of Site
Public Use of Site
Conduct of Operations
Work Restrictions
Special Construction Requirements
Soils Investigation Report
Additional Reports
WORK COVERED BY CONTRACT DOCUMENTS
A.
Project Location: Wyoming
B.
The Work consists of:
1.
C.
1.3
A.
Project will be constructed under a single prime contract.
WORK PHASES
The work shall be coordinated with the Contracting Officer (CO). The work can be performed in
The beginning of the document. Download the full file to read on.
Other documents in this bid
- Attachment 10: General References
- Attachment 4 2026NWPs WY 401WQC
- Attachment 5: Factsheet 2026
- Attachment 6 2026 FinalRegionalConditions WY
- Attachment 7: Project Experience
- Attachment 8: Past Performance Questionnaire
- Sol
- Sol Amendment 0001
- Amendment 2: Pre-Proposal Conference Slides YELL 0002
- Amendment 2: YELL - Pre-Proposal Conference Transcripts 0002
- Sol Amendment 0002